172 S SERRANO AVE 90004
Certificate Information: 172 S SERRANO AVE 90004
- Application / Permit
- 21014-20000-04172
- Plan Check / Job No.
- B21VN11027
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 7'11" X 19'5" ADDITION TO THE (E) ACCESSORY DWELLING UNIT TO ENLARGE (2) BEDROOMS AND ADD NEW BATHROOM AS PER LAMC 12.22.A33 (C) AND (E) , ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 10/15/2021
- Issuing Office
- Current Status
- CofO Issued on 5/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2021 | RARES BODEA |
| Corrections Issued | 8/18/2021 | RARES BODEA |
| Plan Check Approved | 9/9/2021 | RARES BODEA |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| Issued | 10/15/2021 | APPLICANT |
| CofO in Progress | 5/7/2025 | RAUL BARAJAS |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
| CofO Issued | 5/10/2025 | DEROLD HAUFF |
| Permit Finaled | 5/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 8/31/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 11/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 12/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/23/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 12/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/31/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 1/31/2022 | Approved | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 1/31/2022 | Approved | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 1/31/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 2/3/2022 | Conditional Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 2/3/2022 | Approved | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 2/3/2022 | Approved | SHAVONNE ESPINOZA |
| Insulation | 2/11/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 2/28/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/2/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 3/2/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 3/11/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/16/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 3/16/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 3/18/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 3/18/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Insulation | 3/24/2022 | Approved | SHAVONNE ESPINOZA |
| Drywall Nailing | 4/6/2022 | Approved | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 12/1/2022 | Approved | JEFFREY MEAD |
| Final | 12/1/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 12/1/2022 | Approved | JEFFREY MEAD |
| Green Building Final | 12/1/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 12/1/2022 | Partial Approval | JEFFREY MEAD |
| Final | 12/7/2022 | Partial Approval | JEFFREY MEAD |
| Smoke Detectors | 12/7/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 12/13/2022 | Approved | JEFFREY MEAD |
| Final | 12/13/2022 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 12/13/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 12/13/2022 | Approved | JEFFREY MEAD |
| Final | 5/7/2025 | OK to Issue CofO | RAUL BARAJAS |