13548 W GLAMIS ST 91331

Certificate Information: 13548 W GLAMIS ST 91331

Application / Permit
21014-20000-04167
Plan Check / Job No.
B21VN11000
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert (E) Det. Garage into (N) ADU & Add to ADU
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
CofO Issued on 6/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 JOE VO
Corrections Issued 9/19/2021 JOE VO
Quality Review Completed 10/3/2021 HERNAN ARREOLA
Applicant returned to address corrections 11/19/2021 JOE VO
Plan Check Approved 2/16/2022 JOE VO
Issued 3/16/2022 APPLICANT
CofO in Progress 6/8/2023 MICHEL ABAJAN
Permit Finaled 6/9/2023 MICHAEL SMITH
CofO Issued 6/9/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 10/5/2021 GABRIEL ROBLES
Sewer availability Cleared 10/5/2021 GABRIEL ROBLES
Low Impact Development Cleared 11/10/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 11/12/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/5/2022 RIDWAN HARDY

Contact Information

Architect Hefner,, Charles David; Lic. No.: NA23963       ,
Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/26/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/26/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 5/3/2022 Approved MICHEL ABAJAN
Footing/Foundation/Slab 5/5/2022 Approved MICHEL ABAJAN
METHANE-Barrier 5/5/2022 Approved MICHEL ABAJAN
METHANE-Subgrade 5/5/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/13/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/13/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Approval JENNIFER RABUCHIN
Green Building Rough 6/13/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 6/13/2022 Approved JENNIFER RABUCHIN
METHANE-Rough 6/13/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/13/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/23/2022 Approved MICHEL ABAJAN
Shower Pan 6/23/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/7/2022 Approved MICHEL ABAJAN
Green Building Rough 7/7/2022 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 7/7/2022 Approved MICHEL ABAJAN
Insulation 7/12/2022 Approved MICHEL ABAJAN
Drywall Nailing 7/27/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/27/2022 Partial Approval GREGG CUMMINGS
Final 12/28/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 12/28/2022 Approved MICHEL ABAJAN
MERV13>=Final 12/28/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/28/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/28/2022 Approved MICHEL ABAJAN
Final 6/1/2023 Corrections Issued WILLIAM WREN
ELECTRICAL-Final 6/8/2023 Approved MICHEL ABAJAN
Final 6/8/2023 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 6/8/2023 Approved MICHEL ABAJAN
PLUMBING-Final 6/8/2023 Approved MICHEL ABAJAN