13548 W GLAMIS ST 91331
Certificate Information: 13548 W GLAMIS ST 91331
- Application / Permit
- 21014-20000-04167
- Plan Check / Job No.
- B21VN11000
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Convert (E) Det. Garage into (N) ADU & Add to ADU
- Permit Issued
- Issued on 3/16/2022
- Issuing Office
- Current Status
- CofO Issued on 6/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | JOE VO |
| Corrections Issued | 9/19/2021 | JOE VO |
| Quality Review Completed | 10/3/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 11/19/2021 | JOE VO |
| Plan Check Approved | 2/16/2022 | JOE VO |
| Issued | 3/16/2022 | APPLICANT |
| CofO in Progress | 6/8/2023 | MICHEL ABAJAN |
| Permit Finaled | 6/9/2023 | MICHAEL SMITH |
| CofO Issued | 6/9/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/10/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/12/2021 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 1/5/2022 | RIDWAN HARDY |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: NA23963 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/26/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 4/26/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 5/3/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/5/2022 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 5/5/2022 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 5/5/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 6/13/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/13/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/23/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/23/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/7/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/7/2022 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 7/7/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/12/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/27/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/27/2022 | Partial Approval | GREGG CUMMINGS |
| Final | 12/28/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/28/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 12/28/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/28/2022 | Approved | MICHEL ABAJAN |
| Final | 6/1/2023 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Final | 6/8/2023 | Approved | MICHEL ABAJAN |
| Final | 6/8/2023 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 6/8/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/8/2023 | Approved | MICHEL ABAJAN |