11443 W SATICOY ST 91335
Certificate Information: 11443 W SATICOY ST 91335
- Application / Permit
- 21014-20000-04163
- Plan Check / Job No.
- B21VN10990
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert Existing Detached Garage into an DETACHED ADU with a 1 Story addition PER ORDINANCE
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Current Status
- CofO Issued on 8/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | CARLOS MONTES |
| Corrections Issued | 9/4/2021 | CARLOS MONTES |
| Quality Review Completed | 9/13/2021 | WING SUEN |
| Applicant returned to address corrections | 10/27/2021 | CARLOS MONTES |
| Plan Check Approved | 11/12/2021 | CARLOS MONTES |
| Issued | 11/17/2021 | APPLICANT |
| CofO in Progress | 6/22/2022 | CHRISTOPHER DELLEFIELD |
| No Progress | 7/19/2022 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 7/27/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
| CofO Issued | 8/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/15/2021 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 9/16/2021 | ANACANY HURTADO |
| Low Impact Development | Cleared | 10/1/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 10/8/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/14/2022 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/20/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/20/2022 | Approved | GREGG CUMMINGS |
| Sewer | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 4/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/8/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/22/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Green Building Final | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 6/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 7/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 7/27/2022 | Approved | CHRISTOPHER DELLEFIELD |