11443 W SATICOY ST 91335

Certificate Information: 11443 W SATICOY ST 91335

Application / Permit
21014-20000-04163
Plan Check / Job No.
B21VN10990
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert Existing Detached Garage into an DETACHED ADU with a 1 Story addition PER ORDINANCE
Permit Issued
Issued on 11/17/2021
Issuing Office
Current Status
CofO Issued on 8/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 CARLOS MONTES
Corrections Issued 9/4/2021 CARLOS MONTES
Quality Review Completed 9/13/2021 WING SUEN
Applicant returned to address corrections 10/27/2021 CARLOS MONTES
Plan Check Approved 11/12/2021 CARLOS MONTES
Issued 11/17/2021 APPLICANT
CofO in Progress 6/22/2022 CHRISTOPHER DELLEFIELD
No Progress 7/19/2022 CHRISTOPHER DELLEFIELD
CofO in Progress 7/27/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 8/19/2022 DANIEL ORRANTE
CofO Issued 8/19/2022 DANIEL ORRANTE
Permit Finaled 8/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/14/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/15/2021 DAGOVERTO GUERRERO
Clean Up Green Up Cleared 9/16/2021 ANACANY HURTADO
Low Impact Development Cleared 10/1/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/8/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/14/2022 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 1/20/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 1/20/2022 Approved GREGG CUMMINGS
Sewer 3/30/2022 Approved CHRISTOPHER DELLEFIELD
Underground Mechanical 3/30/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 4/5/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 4/5/2022 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 4/8/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 4/12/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 4/15/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/15/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/22/2022 Approved CHRISTOPHER DELLEFIELD
Final 6/22/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Green Building Final 6/22/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 6/22/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 6/22/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 6/22/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 7/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Pre-Inspection 7/27/2022 Approved CHRISTOPHER DELLEFIELD