17354 W SUNBURST ST 91325

Certificate Information: 17354 W SUNBURST ST 91325

Application / Permit
21014-20000-04161
Plan Check / Job No.
B21VN10985
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(15'-0" X 21'-3"),319 SQFT ADDITION TO ENLARGE THE (E) GARAGE SEE COMMENTS.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/17/2021 PETER MOSESIAN
Corrections Issued 8/17/2021 PETER MOSESIAN
Building Plans Picked Up 8/19/2021 APPLICANT
Applicant returned to address corrections 9/17/2021 PETER MOSESIAN
Applicant returned to address corrections 9/29/2021 PETER MOSESIAN
Issued 2/9/2022 APPLICANT
CofO in Progress 12/12/2023 JAVIER RAMOS JR
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/21/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 8/30/2021 CARLOS AGUILERA
ZA Case Cleared 10/28/2021 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2022 Partial Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 3/1/2022 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 3/1/2022 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 3/7/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 3/7/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/25/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Approved RAUL OLAGI
Green Building Rough 3/25/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/31/2022 Corrections Issued RAUL OLAGI
Green Building Rough 3/31/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 3/31/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/7/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/7/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Not Ready JAVIER RAMOS JR
Drywall Nailing 4/14/2022 Approved JAVIER RAMOS JR
Green Building Final 4/14/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 10/30/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 10/30/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 10/30/2023 Approved JAVIER RAMOS JR