10152 N ORO VISTA AVE 91040

Certificate Information: 10152 N ORO VISTA AVE 91040

Application / Permit
21014-20000-04155
Plan Check / Job No.
B21VN10975
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
11'-5" x 12'-7" addition for a new 3/4 bathroom and closet
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 6/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2021 APPLICANT
Assigned to Plan Check Engineer 8/17/2021 ANGELICA DAVE
Corrections Issued 8/17/2021 ANGELICA DAVE
Applicant returned to address corrections 9/3/2021 ANGELICA DAVE
Plan Check Approved 9/14/2021 ANGELICA MARTINEZ
Issued 9/14/2021 APPLICANT
Building Plans Picked Up 9/14/2021 APPLICANT
CofO in Progress 12/22/2021 WILLIAM KUEHN
Permit Finaled 6/11/2022 MICHAEL SMITH
CofO Issued 6/11/2022 MICHAEL SMITH
Permit Finaled 6/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/21/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/23/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 8/24/2021 TIMOTHY POWELL

Contact Information

Contractor Gladiator Construction Inc; Lic. No.: 1015248-B 17412 VENTURA BLVD #372      ENCINO, CA 91316
Engineer Nirattisai,, Preston; Lic. No.: C85115 28411 ASCENT WAY      SANTA CLARITA, CA 91350

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 10/8/2021 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/28/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/28/2021 Approved MATTHEW NELSON
Green Building Rough 10/28/2021 Approved MATTHEW NELSON
PLUMBING-Rough 10/28/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/4/2021 Partial Inspection WILLIAM KUEHN
Shower Pan 11/4/2021 Approved WILLIAM KUEHN
Drywall Nailing 11/12/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/12/2021 Approved MATTHEW NELSON
Final 12/21/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 12/21/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 12/21/2021 Approved WILLIAM KUEHN