4640 N KRAFT AVE 91602

Certificate Information: 4640 N KRAFT AVE 91602

Application / Permit
21014-20000-04143
Plan Check / Job No.
B21VN10938
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION TO (E) ONE STORY SFD
Permit Issued
Issued on 12/30/2021
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 MOHAMMAD ESMAILI
Corrections Issued 9/18/2021 MOHAMMAD ESMAILI
Quality Review Completed 10/8/2021 OMID HEDAYAT
Building Plans Picked Up 10/12/2021 APPLICANT
Applicant returned to address corrections 11/17/2021 MOHAMMAD ESMAILI
Plan Check Approved 12/6/2021 MOHAMMAD ESMAILI
Issued 12/30/2021 APPLICANT
CofO in Progress 1/12/2023 JACK KARGODORIAN
Permit Finaled 1/19/2023 MICHAEL SMITH
CofO Issued 1/19/2023 MICHAEL SMITH
Permit Finaled 1/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Certificate of Compliance Cleared 10/13/2021 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 10/13/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 10/13/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 10/13/2021 DAGOVERTO GUERRERO
ZI Cleared 10/13/2021 DANG NGUYEN
Specific Plan Cleared 10/20/2021 CORREY KITCHENS
ZI Cleared 10/20/2021 CORREY KITCHENS

Contact Information

Contractor Universal Home Design Inc; Lic. No.: 826744-B 5815 WILKINSON AVE      N HOLLYWOOD, CA 91607
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/24/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/4/2022 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 4/5/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 4/11/2022 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 6/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 6/14/2022 Partial Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/11/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 8/11/2022 Corrections Issued CALEB MEISTER
Final 8/11/2022 Corrections Issued CALEB MEISTER
Green Building Rough 8/11/2022 Not Ready for Inspection CALEB MEISTER
HVAC-Rough 8/11/2022 Corrections Issued CALEB MEISTER
MERV13>=Rough 8/11/2022 Approved CALEB MEISTER
PLUMBING-Rough 8/11/2022 Approved CALEB MEISTER
Pre-Inspection 8/16/2022 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Conditional Approval CALEB MEISTER
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection ALAN MORELOS
Green Building Rough 8/29/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 8/29/2022 Not Ready for Inspection ALAN MORELOS
Interior/Exterior Lathing 9/2/2022 Corrections Issued CALEB MEISTER
Insulation 9/8/2022 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 9/14/2022 Conditional Approval THOMAS FINNILA
Green Building Rough 9/14/2022 Approved THOMAS FINNILA
HVAC-Rough 9/14/2022 Approved THOMAS FINNILA
Insulation 9/14/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/14/2022 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 9/20/2022 Conditional Approval CALEB MEISTER
Interior/Exterior Lathing 9/29/2022 Approved ROBERT GOLD
Shower Pan 9/29/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 12/30/2022 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/30/2022 Approved JACK KARGODORIAN
Final 12/30/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 12/30/2022 Approved JACK KARGODORIAN
HVAC-Final 12/30/2022 Approved JACK KARGODORIAN
MERV13>=Final 12/30/2022 Approved JACK KARGODORIAN
PLUMBING-Final 12/30/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/30/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 12/30/2022 Approved JACK KARGODORIAN
Final 1/9/2023 Corrections Issued JACK KARGODORIAN
Final 1/11/2023 OK to Issue CofO JACK KARGODORIAN