9706 S DENKER AVE 90047
Certificate Information: 9706 S DENKER AVE 90047
- Application / Permit
- 21014-20000-04140
- Plan Check / Job No.
- B21VN10933
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (7'-0"x14'-0") 88 SQ. FT. ADDITION OF NEW BEDROOM AND REPLACE ALL WINDOWS TO THE (E) SFD.
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 5/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | PETER MOSESIAN |
| Corrections Issued 2 | 8/22/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| Submitted for Second Quality Review | 9/7/2021 | PETER MOSESIAN |
| Plan Check Approved | 9/9/2021 | PETER MOSESIAN |
| Issued | 10/5/2021 | APPLICANT |
| CofO in Progress | 5/16/2023 | DANIEL GONZALEZ |
| Permit Finaled | 5/16/2023 | BRUCE TODD |
| CofO Issued | 5/16/2023 | BRUCE TODD |
| Permit Finaled | 5/16/2023 | BRUCE TODD |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/27/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN PARKER, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICHAEL SERETTI, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| HECTOR RODRIGUEZ, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| BRUCE TODD, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAVIER RAMOS SR, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIAN PODPORA, (213) 978-4508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 11/4/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 11/4/2021 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Rough | 11/4/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 11/16/2021 | Not Ready for Inspection | KIM DOEPPING |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | KIM DOEPPING |
| Green Building Rough | 11/18/2021 | Approved | KIM DOEPPING |
| METHANE-Rough | 11/18/2021 | Approved | KIM DOEPPING |
| Interior/Exterior Lathing | 12/7/2021 | Approved | KIM DOEPPING |
| Shower Pan | 12/7/2021 | Approved | KIM DOEPPING |
| Drywall Nailing | 3/15/2022 | Approved | KIM DOEPPING |
| Final | 3/15/2022 | Conditional Approval | KIM DOEPPING |
| Footing/Foundation/Slab | 3/15/2022 | Approved | KIM DOEPPING |
| Green Building Final | 3/15/2022 | Approved | KIM DOEPPING |
| METHANE-Barrier | 3/15/2022 | Approved | KIM DOEPPING |
| METHANE-Subgrade | 3/15/2022 | Approved | KIM DOEPPING |
| SGSOV-Seismic Gas S/O Valve | 3/15/2022 | SGSOV Approved | KIM DOEPPING |
| Smoke Detectors | 3/15/2022 | Approved | KIM DOEPPING |
| Final | 5/16/2023 | OK to Issue CofO | DANIEL GONZALEZ |