6724 N WHITE OAK AVE 91406
Certificate Information: 6724 N WHITE OAK AVE 91406
- Application / Permit
- 21014-20000-04119
- Plan Check / Job No.
- B21VN10875
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing garage with addition to 1-Story ADU.
- Permit Issued
- Issued on 5/18/2022
- Issuing Office
- Current Status
- Issued on 5/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | JOE VO |
| Corrections Issued | 8/16/2021 | JOE VO |
| Plan Check Approved | 3/10/2022 | JOE VO |
| Issued | 5/18/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/19/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/14/2021 | KURT CORRAL |
| Construction near power lines | Cleared | 10/25/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 3/3/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 3/3/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 6/28/2023 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 7/24/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 8/16/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Partial Approval | JON MCHUGH |
| ELECTRICAL-Rough | 8/18/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 8/18/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 9/7/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 9/7/2023 | Approved | JON MCHUGH |
| Insulation | 9/18/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 9/18/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 10/4/2023 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 11/22/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 2/27/2024 | Not Ready for Inspection | JON MCHUGH |
| Insulation | 2/27/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/7/2024 | Partial Approval | JEFFREY PARD |
| Shower Pan | 3/7/2024 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/11/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/11/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 3/11/2024 | Approved | JON MCHUGH |
| Insulation | 3/11/2024 | Conditional Approval | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 3/11/2024 | Approved | JON MCHUGH |
| Shower Pan | 3/11/2024 | Not Ready for Inspection | JON MCHUGH |
| Drywall Nailing | 3/26/2024 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/26/2024 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 3/29/2024 | Corrections Issued | HENRY KIM |
| Insulation | 3/29/2024 | Corrections Issued | HENRY KIM |
| Shower Pan | 3/29/2024 | Approved | HENRY KIM |
| Insulation | 4/2/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 5/9/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 5/9/2024 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 9/4/2024 | Approved | JON MCHUGH |
| Final | 9/4/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 9/4/2024 | Not Ready for Inspection | JON MCHUGH |