22163 W ECCLES ST 91304
Certificate Information: 22163 W ECCLES ST 91304
- Application / Permit
- 21014-20000-04117
- Plan Check / Job No.
- B21VN10868
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-11" X 22'-7 1/4" ADDITION AND INTERIOR REMODEL OF (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2021 | PARISA ZAHABI |
| Corrections Issued | 8/25/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 10/20/2021 | PARISA ZAHABI |
| Plan Check Approved | 1/11/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 11/15/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 12/18/2023 | JOHN JANSON |
| CofO Issued | 12/18/2023 | JOHN JANSON |
| Permit Finaled | 12/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/28/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2021 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 10/14/2021 | MANUEL TEJADA |
Contact Information
| Contractor | Treeium Inc; Lic. No.: 617148-B | 5352 LAUREL CANYON BLVD #200 VALLEY VILLAGE, CA 91607 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/17/2023 | Approved | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 7/28/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 7/31/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/9/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 8/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 8/30/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 8/30/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/15/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/15/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/21/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 9/28/2023 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 10/3/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 11/7/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/7/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/7/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/14/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 11/14/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/14/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/14/2023 | Approved | CHRIS CHRISTENSEN |