13389 N GLENOAKS BLVD 91342

Certificate Information: 13389 N GLENOAKS BLVD 91342

Application / Permit
21014-20000-04081
Plan Check / Job No.
B21VN10772
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) CARPORT AND ADD 1ST AND 2ND STORY (19'-9"x40'-0") ADDITION CONSISTING OF A ATTACHED GARAGE (381 SQFT) AND 3 BEDROOMS (1050 SQFT) W/NFPA 13D SPRINKLERS REQ THROUGHOUT
Permit Issued
Issued on 2/15/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 PETER MOSESIAN
Corrections Issued 9/22/2021 PETER MOSESIAN
Quality Review Completed 9/29/2021 OMID HEDAYAT
Building Plans Picked Up 9/30/2021 APPLICANT
Plan Check Approved 2/15/2022 JON BLAINE
Issued 2/15/2022 APPLICANT
CofO in Progress 12/21/2022 MICHAEL SMITH
CofO in Progress 12/21/2022 MICHEL ABAJAN
CofO Issued 12/22/2022 MICHAEL SMITH
Permit Finaled 12/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 1/26/2022 AMIR KASHFI
Low Impact Development Cleared 1/27/2022 TA ANH
Roof/Waste drainage to street Cleared 1/28/2022 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 1/31/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2022 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 3/25/2022 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 5/4/2022 Corrections Issued JOHN HAYES
Green Building Rough 5/4/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 5/4/2022 Partial Approval JOHN HAYES
Deputy Wood Construction 5/9/2022 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 5/10/2022 Partial Approval JOHN HAYES
ELECTRICAL-Rough 5/10/2022 Approved JOHN HAYES
Green Building Rough 5/10/2022 Partial Approval JOHN HAYES
HVAC-Rough 5/10/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/10/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 5/17/2022 Corrections Issued JOHN HAYES
Gas Test 5/17/2022 Approved JOHN HAYES
HVAC-Rough 5/17/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/20/2022 Approved JOHN HAYES
Green Building Rough 5/20/2022 Approved JOHN HAYES
HVAC-Rough 5/20/2022 Approved JOHN HAYES
Insulation 5/31/2022 Approved JOHN HAYES
Drywall Nailing 6/9/2022 Approved JOHN HAYES
Shower Pan 6/9/2022 Approved JOHN HAYES
Final 8/31/2022 Corrections Issued ASHLEY THOMPSON
Green Building Final 8/31/2022 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 8/31/2022 Not Ready for Inspection ASHLEY THOMPSON
Special/Order Compliance 8/31/2022 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Final 12/20/2022 Approved MICHEL ABAJAN
Final 12/20/2022 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 12/20/2022 Approved MICHEL ABAJAN
PLUMBING-Final 12/20/2022 Approved MICHEL ABAJAN
Smoke Detectors 12/20/2022 Approved MICHEL ABAJAN
Final 12/21/2022 OK to Issue CofO MICHAEL SMITH