13403 N GLADSTONE AVE 91342
Certificate Information: 13403 N GLADSTONE AVE 91342
- Application / Permit
- 21014-20000-04079
- Plan Check / Job No.
- B21VN10767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- CONVERT (E) STORAGE WITH ADDITION TO NEW 2-STORY ACCESSORY LIVING QUARTERS (35'-0"x28'-0"), 1443 SQFT
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | PETER MOSESIAN |
| Corrections Issued | 9/19/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/24/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Plan Check Approved | 11/19/2021 | PETER MOSESIAN |
| Issued | 11/23/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | ARAM AVEDISIAN |
| CofO Issued | 7/23/2022 | MICHAEL SMITH |
| Permit Finaled | 7/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/7/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 11/2/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/20/2021 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/5/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/14/2022 | Approved | JOHN HAYES |
| MERV13>=Rough | 1/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 1/19/2022 | Partial Approval | JOHN HAYES |
| Deputy Wood Construction | 2/3/2022 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 3/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 3/4/2022 | Partial Approval | JOHN HAYES |
| MERV13>=Rough | 3/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/4/2022 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | JOHN HAYES |
| Gas Test | 3/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 3/7/2022 | Approved | JOHN HAYES |
| MERV13>=Rough | 3/7/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/7/2022 | Approved | JOHN HAYES |
| Shower Pan | 3/7/2022 | Approved | JOHN HAYES |
| Insulation | 3/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 3/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 3/15/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 3/18/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/18/2022 | Approved | JOHN HAYES |
| Final | 6/17/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 6/17/2022 | Approved | MATT KELLERMAN |
| MERV13>=Final | 6/17/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | MATT KELLERMAN |
| Smoke Detectors | 6/17/2022 | Approved | MATT KELLERMAN |
| ELECTRICAL-Final | 7/21/2022 | Approved | ARAM AVEDISIAN |
| Final | 7/21/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 7/21/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 7/21/2022 | Approved | ARAM AVEDISIAN |