10139-10141 N NOBLE AVE 91345
Certificate Information: 10139-10141 N NOBLE AVE 91345
- Application / Permit
- 21014-20000-04072
- Plan Check / Job No.
- B21VN10735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan CONVERT EXISTING 282 SQ.FT. ROOM TO ADU AND ADD 398 SQ.FT. TO ADU
- Permit Issued
- Issued on 9/28/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/14/2021 | HERNAN ARREOLA |
| Plan Check Approved | 9/12/2021 | HERNAN ARREOLA |
| Issued | 9/28/2021 | APPLICANT |
| CofO in Progress | 8/12/2022 | JENNIFER RABUCHIN |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/23/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/22/2021 | Partial Approval | JENNIFER RABUCHIN |
| Special/Order Compliance | 10/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 2/23/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 2/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 2/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/7/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 3/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/7/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/15/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/15/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/15/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/15/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/30/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/30/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/30/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 4/22/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 4/26/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 5/3/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 7/15/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/4/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 8/15/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/15/2022 | Approved | JENNIFER RABUCHIN |