2663 S ANCHOR AVE 90064

Certificate Information: 2663 S ANCHOR AVE 90064

Application / Permit
21014-20000-04065
Plan Check / Job No.
B21VN10694
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 11' X 11'-10" ADDITION TO ENLARGE KITCHEN, CONVERT 7'-3" X 13'-3" PORTION OF GARAGE TO STORAGE, LAUNDRY & MUDROOM. REMODEL KITCHEN, REMODEL GARAGE AND REROOF. DOORS AND WINDOWS CHANGEOUT. ALL WORK PER DESIGN.
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
Issued on 11/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/11/2021 APPLICANT
Assigned to Plan Check Engineer 8/20/2021 RAPHAEL ROSAS
Corrections Issued 8/22/2021 RAPHAEL ROSAS
Plan Check Approved 11/9/2021 RAPHAEL ROSAS
Building Plans Picked Up 11/12/2021 APPLICANT
Issued 11/18/2021 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/31/2021 PATRICK MISCHLICH
Low Impact Development Cleared 10/19/2021 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/22/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 10/26/2021 HISASHI KOBAYAKAWA

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Seagull Construction & Development; Lic. No.: 1073738-B 1133 S HOPE ST APT 610      LOS ANGELES, CA 90015

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/7/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 12/7/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Barrier 12/7/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 12/7/2021 Not Ready for Inspection KEVIN SARGSYAN
Underground Mechanical 12/7/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/10/2021 Approved EVAN COOPER
Deputy Reinf. Concrete 12/14/2021 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval DEANDRE HOFFMAN
HVAC-Rough 1/14/2022 Corrections Issued DEANDRE HOFFMAN
HVAC-Rough 1/19/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/19/2022 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 1/20/2022 No Access for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2022 No Access for Inspection KEVIN SARGSYAN
Green Building Rough 1/20/2022 No Access for Inspection KEVIN SARGSYAN
METHANE-Rough 1/20/2022 No Access for Inspection KEVIN SARGSYAN
Wood Frame 1/20/2022 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 1/21/2022 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 2/17/2022 Partial Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 2/18/2022 Approved KRISTEN CAUSEY
PLUMBING-Rough 2/18/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 2/25/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 2/25/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 2/25/2022 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 2/25/2022 Approved KEVIN SARGSYAN
Green Building Rough 3/2/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 3/2/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 3/11/2022 Approved KEVIN SARGSYAN
Wood Frame 3/11/2022 Approved KEVIN SARGSYAN
Insulation 3/15/2022 Approved KEVIN SARGSYAN
Drywall Nailing 3/21/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 5/6/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 5/6/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 5/6/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 5/31/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 9/27/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/27/2022 Approved OGANES TARAKHCHYAN
Green Building Final 9/27/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 9/27/2022 Approved OGANES TARAKHCHYAN
METHANE-Barrier 9/27/2022 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 9/27/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/27/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 9/27/2022 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 2/10/2023 Conditional Approval ASHLEY THOMPSON