8745-8747 N GOTHIC AVE 91343
Certificate Information: 8745-8747 N GOTHIC AVE 91343
- Application / Permit
- 21014-20000-04064
- Plan Check / Job No.
- B21VN10693
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 21' X 22' ATTACHED GARAGE AND ADD 12'-6" X 21' TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/27/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/21/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/18/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/15/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2022 | RAPHAEL ROSAS |
| Issued | 4/27/2022 | APPLICANT |
| Building Plans Picked Up | 4/28/2022 | APPLICANT |
| CofO in Progress | 3/29/2023 | RAUL OLAGI |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/24/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 11/2/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C93320 | 6505 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 11/22/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 12/1/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 12/20/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 12/20/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 12/20/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 12/27/2022 | Partial Approval | RAUL OLAGI |
| Green Building Rough | 1/3/2023 | Approved | RAUL OLAGI |
| Insulation | 1/3/2023 | Partial Approval | RAUL OLAGI |
| Interior/Exterior Lathing | 1/3/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 1/9/2023 | Approved | RAUL OLAGI |
| Shower Pan | 1/12/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 1/18/2023 | Approved | RAUL OLAGI |
| Final | 3/21/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 3/21/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 3/21/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 3/21/2023 | Approved | RAUL OLAGI |
| Final | 3/28/2023 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 3/28/2023 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Approved | RAUL OLAGI |