4031-4033 N COLDSTREAM TER 91356
Certificate Information: 4031-4033 N COLDSTREAM TER 91356
- Application / Permit
- 21014-20000-04059
- Plan Check / Job No.
- B21VN10685
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 0INT. REMODEL AND IRREGULAR SHAPED 29' X 19'-10", 10'-4" X 4'-10" ADDITION TO FIRST FLOOR AND 6'-11" X 24' ADDITION AT 2ND FLOOR TO (E) SINGLE FAMILY DWELLING, AND CONVERT 21'-4" X 10'-9" 1 CAR GARAGE AND 15'-5" X 12'-10" PORTION OF SINGLE FAMILY TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Valley
- Current Status
- Issued on 6/27/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/30/2021 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 9/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Applicant returned to address corrections | 11/21/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/5/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/27/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2021 | AMIR KASHFI |
| BHO/Hillside ordinance | Cleared | 12/9/2021 | AMIR KASHFI |
| BHO/Hillside ordinance | Cleared | 12/9/2021 | AMIR KASHFI |
| BHO/Hillside ordinance | Cleared | 12/9/2021 | AMIR KASHFI |
| BHO/Hillside ordinance | Cleared | 12/9/2021 | AMIR KASHFI |
| BHO/Hillside ordinance | Cleared | 12/9/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/9/2021 | AMIR KASHFI |
| Street Frontage | Cleared | 12/9/2021 | AMIR KASHFI |
| ZA Case | Cleared | 12/29/2021 | DANG NGUYEN |
| ZA Case | Cleared | 12/29/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 1/11/2022 | OLGA AYALA |
| Hydrant and Access approval | Cleared | 3/28/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 10/18/2022 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 10/19/2022 | JOSE DUARTE-DIAZ |
| Specific Plan | Cleared | 3/13/2023 | OLGA AYALA |
| GPI Written Notices | Cleared | 4/5/2023 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 4/5/2023 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Amin Farahpour; Lic. No.: 1079005-B | 280 E FAIRVIEW AVE APT 18 GLENDALE, CA 91207 |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/11/2023 | Corrections Issued | SEAN HAUPT |
| Underground Mechanical | 9/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/3/2023 | Approved | SEAN HAUPT |
| Underground Mechanical | 10/3/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/15/2023 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 11/15/2023 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 11/15/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 11/15/2023 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 11/15/2023 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 11/17/2023 | Corrections Issued | SEAN HAUPT |
| Special/Order Compliance | 11/17/2023 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 11/27/2023 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 11/27/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | VINCENT HANLEY |
| Interior/Exterior Lathing | 11/27/2023 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 11/27/2023 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 11/27/2023 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/28/2023 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 11/28/2023 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 11/28/2023 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 12/6/2023 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/11/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 12/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 12/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 12/11/2023 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 12/11/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 12/13/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 12/19/2023 | Approved | SEAN HAUPT |
| Insulation | 12/19/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 1/3/2024 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 1/5/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 1/5/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 5/29/2024 | Corrections Issued | JOHN KIDWELL |
| ELECTRICAL-Final | 8/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Final | 8/6/2024 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 8/28/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/28/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 8/28/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 8/30/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 8/30/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 8/30/2024 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Final | 9/5/2024 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 9/5/2024 | Not Ready for Inspection | JOHN KIDWELL |
| Smoke Detectors | 9/5/2024 | Approved | JOHN KIDWELL |
| HVAC-Final | 9/9/2024 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Final | 9/9/2024 | Partial Inspection | JOHN KIDWELL |
| PLUMBING-Final | 9/11/2024 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 4/8/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 4/8/2025 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 4/8/2025 | Approved | JOHN KIDWELL |
| Service/Power Release | 4/8/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 5/22/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 5/22/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 6/5/2025 | Approved | JOHN KIDWELL |