4031-4033 N COLDSTREAM TER 91356

Certificate Information: 4031-4033 N COLDSTREAM TER 91356

Application / Permit
21014-20000-04059
Plan Check / Job No.
B21VN10685
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
0INT. REMODEL AND IRREGULAR SHAPED 29' X 19'-10", 10'-4" X 4'-10" ADDITION TO FIRST FLOOR AND 6'-11" X 24' ADDITION AT 2ND FLOOR TO (E) SINGLE FAMILY DWELLING, AND CONVERT 21'-4" X 10'-9" 1 CAR GARAGE AND 15'-5" X 12'-10" PORTION OF SINGLE FAMILY TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 6/27/2023
Issuing Office
Valley
Current Status
Issued on 6/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 8/30/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 9/2/2021 OMID HEDAYAT
Building Plans Picked Up 9/7/2021 APPLICANT
Applicant returned to address corrections 11/21/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/5/2023 SEWADA ZADOORAN MILAGARDI
Issued 6/27/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/9/2021 AMIR KASHFI
BHO/Hillside ordinance Cleared 12/9/2021 AMIR KASHFI
BHO/Hillside ordinance Cleared 12/9/2021 AMIR KASHFI
BHO/Hillside ordinance Cleared 12/9/2021 AMIR KASHFI
BHO/Hillside ordinance Cleared 12/9/2021 AMIR KASHFI
BHO/Hillside ordinance Cleared 12/9/2021 AMIR KASHFI
Sewer availability Cleared 12/9/2021 AMIR KASHFI
Street Frontage Cleared 12/9/2021 AMIR KASHFI
ZA Case Cleared 12/29/2021 DANG NGUYEN
ZA Case Cleared 12/29/2021 DANG NGUYEN
Specific Plan Cleared 1/11/2022 OLGA AYALA
Hydrant and Access approval Cleared 3/28/2022 DWIGHT SANKEY
Low Impact Development Cleared 10/18/2022 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 10/19/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 10/19/2022 JOSE DUARTE-DIAZ
Specific Plan Cleared 3/13/2023 OLGA AYALA
GPI Written Notices Cleared 4/5/2023 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 4/5/2023 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Amin Farahpour; Lic. No.: 1079005-B 280 E FAIRVIEW AVE APT 18      GLENDALE, CA 91207
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/11/2023 Corrections Issued SEAN HAUPT
Underground Mechanical 9/11/2023 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 10/3/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 10/3/2023 Approved SEAN HAUPT
Underground Mechanical 10/3/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 11/15/2023 Corrections Issued SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Approved SEAN HAUPT
Green Building Rough 11/15/2023 Not Ready for Inspection SEAN HAUPT
HVAC-Rough 11/15/2023 Approved SEAN HAUPT
PLUMBING-Rough 11/15/2023 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 11/15/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 11/17/2023 Corrections Issued SEAN HAUPT
Special/Order Compliance 11/17/2023 Corrections Issued SEAN HAUPT
BUILDING-Rough-Frame 11/27/2023 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 11/27/2023 Corrections Issued VINCENT HANLEY
Green Building Rough 11/27/2023 Not Ready for Inspection VINCENT HANLEY
Interior/Exterior Lathing 11/27/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 11/27/2023 Partial Approval VINCENT HANLEY
Verify Sprinkler Sign Off 11/27/2023 Not Ready for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 11/28/2023 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 11/28/2023 Partial Approval SEAN HAUPT
PLUMBING-Rough 11/28/2023 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 12/6/2023 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 12/11/2023 Corrections Issued SEAN HAUPT
Green Building Rough 12/11/2023 Not Ready for Inspection SEAN HAUPT
Interior/Exterior Lathing 12/11/2023 Not Ready for Inspection SEAN HAUPT
PLUMBING-Rough 12/11/2023 Approved SEAN HAUPT
Verify Sprinkler Sign Off 12/11/2023 Approved SEAN HAUPT
ELECTRICAL-Rough 12/13/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/13/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 12/15/2023 Approved MORRIS JACKSON
Green Building Rough 12/15/2023 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 12/19/2023 Approved SEAN HAUPT
Green Building Rough 12/19/2023 Approved SEAN HAUPT
Insulation 12/19/2023 Approved SEAN HAUPT
Drywall Nailing 1/3/2024 Corrections Issued HENRY KIM
Drywall Nailing 1/5/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 1/5/2024 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 5/29/2024 Corrections Issued JOHN KIDWELL
ELECTRICAL-Final 8/6/2024 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 8/6/2024 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 8/28/2024 Approved JOHN KIDWELL
HVAC-Final 8/28/2024 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 8/28/2024 Not Ready for Inspection JOHN KIDWELL
Final 8/30/2024 Corrections Issued MORRIS JACKSON
Green Building Final 8/30/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 8/30/2024 Not Ready for Inspection MORRIS JACKSON
HVAC-Final 9/5/2024 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 9/5/2024 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 9/5/2024 Approved JOHN KIDWELL
HVAC-Final 9/9/2024 Partial Inspection JOHN KIDWELL
PLUMBING-Final 9/9/2024 Partial Inspection JOHN KIDWELL
PLUMBING-Final 9/11/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved JOHN KIDWELL
ELECTRICAL-Final 4/8/2025 Approved JOHN KIDWELL
HVAC-Final 4/8/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 4/8/2025 Approved JOHN KIDWELL
Service/Power Release 4/8/2025 Not Ready for Inspection JOHN KIDWELL
Gas Test 5/22/2025 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 5/22/2025 Not Ready for Inspection JOHN KIDWELL
Gas Test 6/5/2025 Approved JOHN KIDWELL