11335-11337 N HERRICK AVE 91331

Certificate Information: 11335-11337 N HERRICK AVE 91331

Application / Permit
21014-20000-04045
Plan Check / Job No.
B21VN10666
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18' X 18'-6" AND 5' X 18'-10" ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 7/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 JEROME MAGAT PALMA
Corrections Issued 8/26/2021 JEROME MAGAT PALMA
Plan Check Approved 11/8/2021 JEROME MAGAT PALMA
Building Plans Picked Up 11/19/2021 APPLICANT
Issued 12/2/2021 APPLICANT
CofO in Progress 7/23/2022 MICHEL ABAJAN
Permit Finaled 7/30/2022 DEROLD HAUFF
CofO Issued 7/30/2022 DEROLD HAUFF
Permit Finaled 7/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/28/2021 CARLOS AGUILERA
Address approval Cleared 9/28/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/15/2021 CARLOS AGUILERA
Sewer availability Cleared 10/15/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 10/20/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Mario Alberto; Lic. No.: C89006 43023 40TH ST WEST      LANCASTER, CA 93536

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/22/2022 Partial Approval JENNIFER RABUCHIN
Sewer 2/22/2022 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 3/1/2022 No Access for Inspection MICHEL ABAJAN
Deputy Wood Construction 3/10/2022 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 3/24/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 3/24/2022 Partial Inspection MICHEL ABAJAN
HVAC-Rough 3/24/2022 Approved MICHEL ABAJAN
MERV13>=Rough 3/24/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 3/24/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/28/2022 Approved MICHEL ABAJAN
Green Building Rough 4/28/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/28/2022 Approved MICHEL ABAJAN
Insulation 5/11/2022 Conditional Approval KRISTEN CAUSEY
Interior/Exterior Lathing 5/11/2022 Partial Approval KRISTEN CAUSEY
Final 6/16/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 6/16/2022 Approved MICHEL ABAJAN
MERV13>=Final 6/16/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 6/16/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/22/2022 Approved MICHEL ABAJAN
Final 7/22/2022 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 7/22/2022 Approved MICHEL ABAJAN
PLUMBING-Final 7/22/2022 Approved MICHEL ABAJAN