8430-8432 N RANCHITO AVE 91402
Certificate Information: 8430-8432 N RANCHITO AVE 91402
- Application / Permit
- 21014-20000-04043
- Plan Check / Job No.
- B21VN10663
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 8'-3" X 19'-2" PORTION OF (E) SFD AND ADD 20'-6" X 30'-2" FOR (N) ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/14/2023
- Issuing Office
- Current Status
- CofO Issued on 2/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/22/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/13/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Applicant returned to address corrections | 10/3/2022 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/24/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 3/14/2023 | ALEC MOUSAKHANIAN |
| Issued | 3/14/2023 | APPLICANT |
| CofO in Progress | 1/20/2025 | VINCENT HANLEY |
| Permit Finaled | 2/11/2025 | RUBEN SALAS |
| CofO Issued | 2/11/2025 | RUBEN SALAS |
| Permit Finaled | 2/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/25/2021 | GABRIEL ROBLES |
| ZA Case | Cleared | 8/26/2021 | DANG NGUYEN |
| Construction near power lines | Cleared | 11/2/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/30/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 11/30/2021 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/7/2023 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 8/9/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/15/2023 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/28/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/11/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/29/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 1/29/2024 | Approved | GREGG CUMMINGS |
| Sewer | 1/29/2024 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 1/29/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/15/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/15/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 2/15/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/15/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/15/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 2/15/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/1/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 3/1/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 4/3/2024 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 4/8/2024 | Corrections Issued | KIRK SANDERS |
| Insulation | 4/19/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/7/2024 | Approved | GREGG CUMMINGS |
| Final | 9/10/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/10/2024 | Approved | GREGG CUMMINGS |
| Green Building Final | 9/10/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 9/10/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/8/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/8/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/8/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 10/8/2024 | Approved | GREGG CUMMINGS |
| Final | 12/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/26/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/16/2025 | Approved | VINCENT HANLEY |
| Final | 1/16/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 1/16/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/16/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/16/2025 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 2/4/2025 | Conditional Approval | ROBERT GOLD |