145 W 118TH PL 90061

Certificate Information: 145 W 118TH PL 90061

Application / Permit
21014-20000-04037
Plan Check / Job No.
B21VN10638
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19'-9" X 20'-2" DETACHED GARAGE AND ADD 6'-8" X 16'-5" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 08/19/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/20/2021 RAPHAEL ROSAS
Corrections Issued 8/22/2021 RAPHAEL ROSAS
Plan Check Approved 1/13/2022 RAPHAEL ROSAS
Building Plans Picked Up 1/14/2022 APPLICANT
Issued 2/9/2022 APPLICANT
CofO in Progress 3/21/2023 JAMES CHAVEZ
CofO Issued 3/21/2023 ANSON MAGLASANG
Permit Finaled 3/21/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/29/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 9/29/2021 JEANIE LAM
Sewer availability Cleared 10/4/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/3/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/27/2022 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 6/1/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/21/2022 Approved JOHN KLARIN
Deputy Drilled-In Anchors 7/20/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/28/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 7/28/2022 Corrections Issued JOHN KLARIN
Gas Test 7/28/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 7/28/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 7/28/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 7/28/2022 Corrections Issued JOHN KLARIN
Insulation 8/1/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 8/1/2022 Approved EUGENE CASSIDY
Insulation 8/3/2022 Approved JOHN KLARIN
Wood Frame 8/3/2022 Approved JOHN KLARIN
Drywall Nailing 9/6/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 9/6/2022 Approved ALIZAH MAYAGOITIA
Gas Test 9/6/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/6/2022 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 9/6/2022 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 9/30/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/16/2022 Approved JOHN KLARIN
Final 11/16/2022 Corrections Issued JOHN KLARIN
Green Building Final 11/16/2022 Corrections Issued JOHN KLARIN
Green Building Rough 11/16/2022 Approved JOHN KLARIN
MERV13>=Final 11/16/2022 Approved JOHN KLARIN
MERV13>=Rough 11/16/2022 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 11/16/2022 SGSOV Approved JOHN KLARIN
Smoke Detectors 11/16/2022 Approved JOHN KLARIN
Final 12/28/2022 OK to Issue CofO JAMES CHAVEZ
Green Building Final 12/28/2022 Approved JAMES CHAVEZ
Service/Power Release 1/19/2023 Approved JAMES CHAVEZ