3091 W COLISEUM ST 90018
Certificate Information: 3091 W COLISEUM ST 90018
- Application / Permit
- 21014-20000-04030
- Plan Check / Job No.
- B21VN10619
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 11' X 9'-4" AND 3'-11" X 8'-8"ADDITIONS TO (E) GARAGE AND CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEEING.
- Permit Issued
- Issued on 2/1/2022
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2021 | OMAR GARNICA |
| Corrections Issued | 8/30/2021 | OMAR GARNICA |
| Plan Check Approved | 12/7/2021 | OMAR GARNICA |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Issued | 2/1/2022 | APPLICANT |
| CofO in Progress | 9/7/2023 | CHARLES BOGHOSKHAN |
| CofO Issued | 9/13/2023 | DEROLD HAUFF |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 9/10/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 9/17/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 11/22/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Anchor Design & Build; Lic. No.: 1064763-B | 3106 E COLORADO BLVD #5818 PASADENA, CA 91117 |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| Sewer | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/10/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/22/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 7/29/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2022 | Partial Approval | HORACE FULTZ |
| HVAC-Rough | 7/29/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 7/29/2022 | Approved | HORACE FULTZ |
| Wood Frame | 7/29/2022 | Corrections Issued | HORACE FULTZ |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Not Ready for Inspection | HORACE FULTZ |
| Green Building Rough | 8/29/2022 | Approved | HORACE FULTZ |
| Wood Frame | 8/29/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 9/9/2022 | Partial Approval | HORACE FULTZ |
| Insulation | 10/3/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 10/14/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/4/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/4/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 4/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 4/12/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 4/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Final | 4/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 4/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 4/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/1/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 7/13/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Green Building Final | 7/13/2023 | Approved | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | CHARLES BOGHOSKHAN |
| Smoke Detectors | 7/13/2023 | Approved | CHARLES BOGHOSKHAN |
| Final | 9/6/2023 | OK to Issue CofO | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Approved | CHARLES BOGHOSKHAN |