12422 W SARAH ST 91604

Certificate Information: 12422 W SARAH ST 91604

Application / Permit
21014-20000-04026
Plan Check / Job No.
B21VN10614
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-2" X 20'-3" DETACHED GARAGE AND ADD 9' X 17'-3" FOR (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 RAPHAEL ROSAS
Corrections Issued 8/19/2021 RAPHAEL ROSAS
Plan Check Approved 12/7/2021 RAPHAEL ROSAS
Building Plans Picked Up 12/8/2021 APPLICANT
Issued 1/12/2022 APPLICANT
CofO in Progress 8/18/2022 CHRISTOPHE COCHRAN
CofO in Progress 8/18/2022 CHRISTOPHE COCHRAN
Permit Finaled 8/24/2022 DANIEL ORRANTE
CofO Issued 8/24/2022 DANIEL ORRANTE
Permit Finaled 8/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/8/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/8/2021 GABRIEL ROBLES
Sewer availability Cleared 9/8/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/9/2021 GABRIEL ROBLES
Construction near power lines Cleared 11/22/2021 RIDWAN HARDY
ZI Cleared 11/23/2021 STEVEN WECHSLER

Contact Information

Contractor Anchor Design & Build; Lic. No.: 1064763-B 3106 E COLORADO BLVD #5818      PASADENA, CA 91117
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/18/2022 Partial Approval ARAM AVEDISIAN
Pre-Inspection 1/18/2022 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 1/24/2022 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 1/26/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 3/25/2022 Not Ready for Inspection CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 3/25/2022 Partial Approval CALEB MEISTER
HVAC-Rough 3/25/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 3/25/2022 Approved CALEB MEISTER
ELECTRICAL-Rough 4/8/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 4/8/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 5/5/2022 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 5/5/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved ARAM AVEDISIAN
HVAC-Rough 5/5/2022 Approved ARAM AVEDISIAN
MERV13>=Rough 5/5/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 5/23/2022 Partial Approval CALEB MEISTER
Insulation 5/27/2022 Approved CALEB MEISTER
Underground Mechanical 5/27/2022 Partial Approval CALEB MEISTER
Drywall Nailing 6/8/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/29/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/29/2022 Approved CHRISTOPHE COCHRAN
Final 7/29/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 7/29/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 7/29/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 7/29/2022 Approved CHRISTOPHE COCHRAN
HVAC-Final 7/29/2022 Approved CHRISTOPHE COCHRAN
MERV13>=Final 7/29/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 7/29/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 7/29/2022 Approved CHRISTOPHE COCHRAN
Final 8/16/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 8/16/2022 Approved CHRISTOPHE COCHRAN