8439 W APPERSON ST 91040
Certificate Information: 8439 W APPERSON ST 91040
- Application / Permit
- 21014-20000-04025
- Plan Check / Job No.
- B21VN10604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting (E) 365 SQ. FT. garage with Addition (N) 433 SQ. FT. into 798 sq. ft. ADU per state law and LAMC 12.22 A.33 (c)(d)
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/14/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/20/2023 | MICHAEL LANZONE |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 2/13/2024 | DAVID ANDERSON |
| CofO in Progress | 2/14/2024 | DAVID ANDERSON |
| CofO in Progress | 3/13/2024 | DAVID ANDERSON |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/1/2022 | RIDWAN HARDY |
| Address approval | Cleared | 12/22/2022 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2022 | ANA SORIANO |
| Sewer availability | Cleared | 12/27/2022 | ANA SORIANO |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | ANA SORIANO |
| GPI Written Notices | Cleared | 4/20/2023 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 4/20/2023 | MICHAEL LANZONE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimi,, Amirhosin; Lic. No.: C92049 | 8619 RESEDA BLVD UNIT 304B NORTHRIDGE, CA 91324 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 6/2/2023 | Partial Approval | DAVID ANDERSON |
| Pre-Inspection | 6/9/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Approved | DAVID ANDERSON |
| Deputy Reinf. Concrete | 6/22/2023 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | DAVID ANDERSON |
| Wood Frame | 7/10/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 7/25/2023 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 7/25/2023 | Approved | DAVID ANDERSON |
| Insulation | 7/31/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/31/2023 | Partial Approval | WILLIAM WREN |
| Shower Pan | 7/31/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 8/4/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/10/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 9/18/2023 | Approved | DAVID ANDERSON |
| Final | 1/8/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/8/2024 | Approved | DAVID ANDERSON |
| Green Building Final | 1/8/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 1/8/2024 | Approved | DAVID ANDERSON |
| Final | 2/12/2024 | Conditional Approval | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Approved | DAVID ANDERSON |
| Special/Order Compliance | 2/14/2024 | Corrections Issued | DAVID ANDERSON |
| Final | 3/12/2024 | OK to Issue CofO | DAVID ANDERSON |