2217 S SYCAMORE AVE 90016
Certificate Information: 2217 S SYCAMORE AVE 90016
- Application / Permit
- 21014-20000-04022
- Plan Check / Job No.
- B21VN10602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX. DETACHED GARAGE WITH IRREGULAR ADDITION ( 24'-0" X 33'-6" ) INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). RE-FRAME ENTIRE BLDG EXCEPT (16'-4" X 4'-0" ) PORTION OF EX. GARAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | RAPHAEL ROSAS |
| Corrections Issued | 8/22/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 8/30/2021 | APPLICANT |
| Plan Check Approved | 8/2/2022 | ROSENDO MEDINA |
| Issued | 8/2/2022 | APPLICANT |
| CofO in Progress | 4/5/2023 | CALEB MEISTER |
| CofO Issued | 4/15/2023 | DEROLD HAUFF |
| Permit Finaled | 4/15/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/12/2021 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 5/22/2022 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/23/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/19/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 9/19/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/21/2022 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 9/21/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 10/5/2022 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 10/5/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 10/5/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/20/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 10/20/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 10/20/2022 | Approved | STUART CHAPMAN |
| Insulation | 10/21/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 10/26/2022 | Approved | RUBEN SALAS |
| Pre-Inspection | 1/6/2023 | Partial Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 3/15/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 3/15/2023 | Approved | CALEB MEISTER |
| Final | 3/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 3/15/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 3/15/2023 | Approved | CALEB MEISTER |
| MERV13>=Final | 3/15/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 3/15/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 3/15/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 3/15/2023 | Approved | CALEB MEISTER |
| Final | 4/5/2023 | OK to Issue CofO | CALEB MEISTER |