8957-8959 N MONOGRAM AVE 91343

Certificate Information: 8957-8959 N MONOGRAM AVE 91343

Application / Permit
21014-20000-04007
Plan Check / Job No.
B21VN10557
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 132 SQFT ADDITION TO AND CONVERT THE (E) 378 SQFT GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/27/2021
Issuing Office
Current Status
CofO Issued on 4/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 JEFFREY TANGONAN
Corrections Issued 8/14/2021 JEFFREY TANGONAN
Issued 8/27/2021 APPLICANT
Building Plans Picked Up 8/31/2021 APPLICANT
CofO in Progress 3/31/2022 RAUL OLAGI
Permit Finaled 4/4/2022 RONALD MYRICK
Permit Finaled 4/4/2022 RONALD MYRICK
CofO Issued 4/4/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/19/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/19/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 8/19/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/19/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/27/2021 Partial Approval AMY COLIN
Sewer 9/27/2021 Approved AMY COLIN
Footing/Foundation/Slab 10/4/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 10/25/2021 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 11/10/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Approved RAUL OLAGI
PLUMBING-Rough 11/10/2021 Approved RAUL OLAGI
BUILDING-Rough-Frame 12/6/2021 Approved RAUL OLAGI
Green Building Rough 12/6/2021 Approved RAUL OLAGI
HVAC-Rough 12/6/2021 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 12/6/2021 Partial Approval RAUL OLAGI
Shower Pan 12/6/2021 Approved RAUL OLAGI
Insulation 12/9/2021 Approved ALAN MORELOS
Drywall Nailing 12/15/2021 Approved RAUL OLAGI
Pre-Inspection 12/15/2021 No Access for Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 1/12/2022 Approved ALAN MORELOS
ELECTRICAL-Final 3/9/2022 Approved RAUL OLAGI
Final 3/9/2022 Corrections Issued RAUL OLAGI
Green Building Final 3/9/2022 Approved RAUL OLAGI
HVAC-Final 3/9/2022 Approved RAUL OLAGI
PLUMBING-Final 3/9/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 3/9/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 3/9/2022 Approved RAUL OLAGI
Final 3/30/2022 OK to Issue CofO RAUL OLAGI