8344 N SYLMAR AVE 91402
Certificate Information: 8344 N SYLMAR AVE 91402
- Application / Permit
- 21014-20000-04005
- Plan Check / Job No.
- B21VN10549
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 12'6" X 15'6" Addition and converstion of Garge to ADU per Ord 186481
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | HERNAN ARREOLA |
| Corrections Issued | 8/16/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/23/2021 | HERNAN ARREOLA |
| Plan Check Approved | 11/22/2021 | HERNAN ARREOLA |
| Issued | 12/3/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | GREGG CUMMINGS |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/21/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 11/13/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 1/27/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 1/31/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/31/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 1/31/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/4/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 4/4/2022 | Partial Approval | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Sewer | 4/4/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2022 | Partial Approval | GREGG CUMMINGS |
| Gas Test | 4/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 4/25/2022 | Partial Approval | GREGG CUMMINGS |
| Gas Test | 5/5/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 5/5/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 5/9/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 5/9/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/9/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 5/16/2022 | Approved | WILLIAM WREN |
| Insulation | 5/16/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 5/20/2022 | Approved | WILLIAM WREN |
| Light Gage Steel Frame | 6/10/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 6/23/2022 | Approved | MICHAEL SMITH |
| Final | 9/8/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 9/8/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/8/2022 | Approved | MATTHEW NELSON |
| Final | 11/14/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 12/12/2022 | Approved | GREGG CUMMINGS |
| Final | 12/12/2022 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 12/12/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 12/12/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 12/12/2022 | Approved | GREGG CUMMINGS |