1837 S OGDEN DR 90019

Certificate Information: 1837 S OGDEN DR 90019

Application / Permit
21014-20000-04003
Plan Check / Job No.
B21VN10540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION ( 15'-2" x 13' ) TO AND CONVERT (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/18/2021 ROSENDO MEDINA
Corrections Issued 8/21/2021 ROSENDO MEDINA
Applicant returned to address corrections 1/11/2022 ROSENDO MEDINA
Plan Check Approved 1/12/2022 ROSENDO MEDINA
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/19/2022 APPLICANT
CofO in Progress 11/22/2022 JOSE AVILA
Permit Finaled 1/13/2023 DEROLD HAUFF
CofO Issued 1/13/2023 DEROLD HAUFF
Permit Finaled 1/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/30/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/30/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 8/30/2021 THOMAS LANG
Sewer availability Cleared 8/30/2021 THOMAS LANG
Construction near power lines Cleared 11/2/2021 RIDWAN HARDY

Contact Information

Contractor Sklar Construction Inc; Lic. No.: 1034994-B 2523 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Mauricio,, Omar; Lic. No.: C87487 947 E MERCED AVE      WEST COVINA, CA 91790

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/4/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/10/2022 Approved JOSE AVILA
Footing/Foundation/Slab 3/10/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 3/14/2022 Approved JOSE AVILA
ELECTRICAL-Rough 4/12/2022 Partial Approval JOSE AVILA
PLUMBING-Rough 4/12/2022 Approved JOSE AVILA
Wood Frame 4/12/2022 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 4/22/2022 Corrections Issued JOSE AVILA
Green Building Rough 4/22/2022 Corrections Issued JOSE AVILA
HVAC-Rough 4/22/2022 Corrections Issued JOSE AVILA
Underground Mechanical 4/22/2022 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/29/2022 Approved JOSE AVILA
Green Building Rough 4/29/2022 Approved JOSE AVILA
Insulation 5/5/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/5/2022 Approved JOSE AVILA
Drywall Nailing 5/13/2022 Approved JOSE AVILA
Interior/Exterior Lathing 6/7/2022 Approved JOSE AVILA
Shower Pan 6/7/2022 Approved JOSE AVILA
ELECTRICAL-Final 7/12/2022 Approved JOSE AVILA
Final 7/12/2022 Corrections Issued JOSE AVILA
Green Building Final 7/12/2022 Corrections Issued JOSE AVILA
HVAC-Final 7/12/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 7/12/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 7/12/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 7/19/2022 Approved JOSE AVILA
Final 7/19/2022 OK to Issue CofO JOSE AVILA
Gas Test 7/19/2022 Approved JOSE AVILA
Green Building Final 7/19/2022 Approved JOSE AVILA
HVAC-Final 7/19/2022 Approved JOSE AVILA
PLUMBING-Final 7/19/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved JOSE AVILA
Service/Power Release 7/19/2022 Approved JOSE AVILA
Smoke Detectors 7/19/2022 Approved JOSE AVILA