1902 N REDCLIFF ST 90039

Certificate Information: 1902 N REDCLIFF ST 90039

Application / Permit
21014-20000-03987
Plan Check / Job No.
B21VN10473
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD ( 36'-7"x 43'-0") IRR SHAPE & FIRE DAMAGE REBUILD PER SEC 12.23 A5 (b) AND MAJOR REMODEL OF (E) TWO STORY SINGLE FAMILY DWELLING, NFPA-13-D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 TROY DEGUZMAN
Corrections Issued 8/31/2021 TROY DEGUZMAN
Quality Review Completed 8/31/2021 OMID HEDAYAT
Building Plans Picked Up 9/1/2021 APPLICANT
Applicant returned to address corrections 10/7/2021 TROY DEGUZMAN
Plan Check Approved 11/18/2021 TROY DEGUZMAN
Issued 12/1/2021 APPLICANT
CofO in Progress 4/13/2023 THOMAS LOGRASSO
Permit Finaled 4/15/2023 DEROLD HAUFF
CofO Issued 4/15/2023 DEROLD HAUFF
Permit Finaled 4/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 9/9/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/13/2021 JEANIE LAM
Sewer availability Cleared 9/13/2021 JEANIE LAM
GPI Written Notices Cleared 10/7/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 10/7/2021 TROY DEGUZMAN
Green Code Cleared 10/7/2021 TROY DEGUZMAN
Construction near power lines Cleared 10/21/2021 WALTER RAMIREZ
Low Impact Development Cleared 10/27/2021 JONATAN VELASQUEZ
Hydrant and Access approval Cleared 10/28/2021 RUEL COLE
Roof/Waste drainage to street Cleared 10/29/2021 JEANIE LAM

Contact Information

Contractor Blue Pacific Contractors Inc; Lic. No.: 1022139-B 13535 LAZARD ST      SAN FERNANDO, CA 91340
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Geologist Robles,, Gustavo; Lic. No.: EG2422 981 W. ARROW HIGHWAY #191      SAN DIMAS, CA 91773

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2021 Partial Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 1/12/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 1/14/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/14/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 1/14/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Partial Approval THOMAS LOGRASSO
Insulation 1/26/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 1/26/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 3/15/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 3/31/2022 Approved ADAM ESCOTO
HVAC-Rough 4/15/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/6/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 5/6/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 5/6/2022 Approved THOMAS LOGRASSO
Insulation 5/26/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 6/6/2022 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 6/6/2022 Conditional Approval THOMAS LOGRASSO
Green Building Rough 6/6/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 6/6/2022 Conditional Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/13/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 6/13/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 8/8/2022 Partial Approval THOMAS LOGRASSO
Green Building Rough 8/8/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 12/12/2022 Approved THOMAS LOGRASSO
PLUMBING-Final 12/12/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Final 1/30/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 1/30/2023 Approved THOMAS LOGRASSO
HVAC-Final 3/8/2023 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 3/30/2023 Approved THOMAS LOGRASSO
Drywall Nailing 3/30/2023 Approved THOMAS LOGRASSO
Final 3/30/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 3/30/2023 Approved THOMAS LOGRASSO
Green Building Final 3/30/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 3/30/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 3/30/2023 Approved THOMAS LOGRASSO
Final 4/13/2023 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 4/13/2023 Approved THOMAS LOGRASSO