17215 W STAGG ST 91406

Certificate Information: 17215 W STAGG ST 91406

Application / Permit
21014-20000-03983
Plan Check / Job No.
B21VN10463
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10' X 40' IRREGULAR SHAPED & 2'-5" X 8'-3" ADDITIONS AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 5/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 RAPHAEL ROSAS
Corrections Issued 8/15/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/14/2021 RAPHAEL ROSAS
Plan Check Approved 2/22/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/23/2022 APPLICANT
Issued 3/17/2022 APPLICANT
CofO in Progress 5/19/2023 RAUL OLAGI
Permit Finaled 5/23/2023 MICHAEL SMITH
CofO Issued 5/23/2023 MICHAEL SMITH
Permit Finaled 5/23/2023 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 11/18/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/22/2021 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 12/1/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael Fernandez; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/20/2022 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 5/24/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 8/2/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/15/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Partial Approval RAUL OLAGI
Green Building Rough 8/15/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 8/15/2022 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Partial Approval RAUL OLAGI
Insulation 8/19/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 9/6/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 10/24/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 10/24/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 11/2/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 11/2/2022 Approved RAUL OLAGI
HVAC-Rough 11/2/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 11/2/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 11/4/2022 Approved RAUL OLAGI
HVAC-Rough 11/4/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/10/2022 Not Ready for Inspection RAUL OLAGI
Green Building Rough 11/18/2022 Approved RAUL OLAGI
Insulation 11/18/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/18/2022 Partial Approval RAUL OLAGI
Drywall Nailing 11/29/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/29/2022 Partial Approval RAUL OLAGI
Shower Pan 11/29/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 12/7/2022 Approved RAUL OLAGI
Final 4/25/2023 Corrections Issued RAUL OLAGI
Green Building Final 4/25/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/25/2023 Approved RAUL OLAGI
Final 5/19/2023 OK to Issue CofO RAUL OLAGI
Service/Power Release 5/19/2023 Approved RAUL OLAGI