5726 W BRUSHTON ST 90008

Certificate Information: 5726 W BRUSHTON ST 90008

Application / Permit
21014-20000-03978
Plan Check / Job No.
B21VN10447
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10' x 15'-9" addition to rear of single-family dwelling to extend existing bedroom and for a new full bathroom
Permit Issued
Issued on 4/25/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 ANGELICA DAVE
Corrections Issued 8/9/2021 ANGELICA DAVE
Plan Check Approved 10/27/2021 ANGELICA MARTINEZ
No Progress 5/26/2022 ANGELICA MARTINEZ
Building Plans Picked Up 6/8/2022 APPLICANT
Plan Check Approved 9/6/2022 ANGELICA MARTINEZ
Issued 4/25/2023 APPLICANT
CofO in Progress 11/15/2023 ANTHONY EGSON
Permit Finaled 11/21/2023 DEROLD HAUFF
CofO Issued 11/21/2023 DEROLD HAUFF
Permit Finaled 11/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 9/27/2021 JASON SHEETS
Hold Cleared 9/27/2021 JEREMY CORONEL
Roof/Waste drainage to street Cleared 10/15/2021 THOMAS LANG
Grading Pre-Inspection Cleared 10/19/2021 ANGELICA MARTINEZ
Eng Process Fee Ord 176,300 Cleared 10/22/2021 THOMAS LANG
Miscellaneous Cleared 8/16/2022 EDMOND LEE

Contact Information

Architect Newbern,, Walter Pedro; Lic. No.: C22914 1010 NO. MADISON AVENUE      PASADENA, CA 91104
Contractor Sheibani Ali M; Lic. No.: 821206-B 15760 VENTURA BLVD #700      ENCINO, CA 91436
Engineer Tsai,, Willy Y; Lic. No.: C35589 1545 RUBIO DR      SAN MARINO, CA 91108

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2023 Corrections Issued ANTHONY EGSON
METHANE-Barrier 5/9/2023 Approved ANTHONY EGSON
METHANE-Subgrade 5/9/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 5/18/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/7/2023 Corrections Issued ANTHONY EGSON
Wood Frame 6/7/2023 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 6/13/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/13/2023 Not Ready for Inspection ANTHONY EGSON
Wood Frame 6/13/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 6/15/2023 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 6/15/2023 Approved ANTHONY EGSON
Wood Frame 6/15/2023 Approved ANTHONY EGSON
Deputy Wood Construction 6/16/2023 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/21/2023 Approved ANTHONY EGSON
HVAC-Rough 6/21/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/21/2023 Approved ANTHONY EGSON
PLUMBING-Rough 6/21/2023 Approved ANTHONY EGSON
Insulation 6/26/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/26/2023 Approved ANTHONY EGSON
Drywall Nailing 6/30/2023 Approved ANTHONY EGSON
Green Building Rough 6/30/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 8/8/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 8/8/2023 Approved ANTHONY EGSON
Final 8/8/2023 Corrections Issued ANTHONY EGSON
Green Building Final 8/8/2023 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 8/8/2023 Approved ANTHONY EGSON
METHANE-Final 8/8/2023 Approved ANTHONY EGSON
METHANE-Rough 8/8/2023 Approved ANTHONY EGSON
PLUMBING-Final 8/8/2023 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved ANTHONY EGSON
Smoke Detectors 8/8/2023 Not Ready for Inspection ANTHONY EGSON
Final 9/20/2023 Corrections Issued ANTHONY EGSON
Green Building Final 9/20/2023 Approved ANTHONY EGSON
Smoke Detectors 9/20/2023 Approved ANTHONY EGSON
Final 11/14/2023 OK to Issue CofO ANTHONY EGSON