10143 N PLAINVIEW AVE 91042

Certificate Information: 10143 N PLAINVIEW AVE 91042

Application / Permit
21014-20000-03973
Plan Check / Job No.
B21VN10436
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 23'6" X 4'9" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE NEW MASTER BEDROOM , MASTER W.I.C., NEW 11' X 5' IRREGULAR SHAPED ADDITION TO (E) SFD TO ENLARGE LIVING ROOM , MAJOR REMODEL TO (E) SFD TO REMOVE ALL INTERIOR WALLS , REMOVE PORTION OF EXTERIOR WALLS , REMODEL (2) BEDROOMS, (1) BATHROOMS, KITCHEN , LIVING ROOM CREATE (1) BATHROOM, POWDER ROOM , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/19/2022
Issuing Office
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 RARES BODEA
Corrections Issued 9/28/2021 RARES BODEA
Quality Review Completed 10/4/2021 STEVEN KIM
Building Plans Picked Up 10/5/2021 APPLICANT
Applicant returned to address corrections 5/5/2022 RARES BODEA
Plan Check Approved 6/2/2022 RARES BODEA
Issued 7/19/2022 APPLICANT
CofO in Progress 7/12/2023 DAVID ANDERSON
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/15/2022 CARLOS AGUILERA
Sewer availability Cleared 3/15/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/1/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 4/19/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/26/2022 DWIGHT SANKEY

Contact Information

Contractor Melkonyan Artsvik; Lic. No.: 1016658-B 921 E CEDAR AVE      BURBANK, CA 91501
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/2/2022 Conditional Approval DAVID ANDERSON
Footing/Foundation/Slab 9/14/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved DAVID ANDERSON
Green Building Rough 11/4/2022 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 11/28/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 11/28/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 12/5/2022 Approved DAVID ANDERSON
HVAC-Rough 12/5/2022 Corrections Issued DAVID ANDERSON
BUILDING-Rough-Frame 12/13/2022 Corrections Issued DAVID ANDERSON
Green Building Rough 12/13/2022 Not Ready for Inspection DAVID ANDERSON
HVAC-Rough 12/13/2022 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 12/15/2022 Approved DAVID ANDERSON
HVAC-Rough 12/15/2022 Approved DAVID ANDERSON
Wood Frame 12/28/2022 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 1/17/2023 Approved DAVID ANDERSON
Green Building Rough 1/17/2023 Approved DAVID ANDERSON
Insulation 1/27/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/27/2023 Approved DAVID ANDERSON
Drywall Nailing 1/31/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 3/2/2023 Approved DAVID ANDERSON
Shower Pan 3/2/2023 Approved DAVID ANDERSON
Final 7/5/2023 Corrections Issued DAVID ANDERSON
Green Building Final 7/5/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/5/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 7/5/2023 Approved DAVID ANDERSON
Final 7/11/2023 OK to Issue CofO DAVID ANDERSON