16718 W ARMSTEAD ST 91344

Certificate Information: 16718 W ARMSTEAD ST 91344

Application / Permit
21014-20000-03958
Plan Check / Job No.
B21VN10405
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 38'-8" X 20'-10" TWO STORY ACCESSORY DWELLING UNIT (1132 SQ FT) PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED STORAGE (764 SQ FT) TO EXISTING 1-STORY GARAGE “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/17/2022
Issuing Office
Current Status
CofO Issued on 3/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SELLA BENYAMIN
Corrections Issued 9/16/2021 SELLA BENYAMIN
Quality Review Completed 9/22/2021 STEVEN KIM
Building Plans Picked Up 9/22/2021 APPLICANT
Plan Check Approved 1/13/2022 SELLA BENYAMIN
Issued 1/17/2022 APPLICANT
CofO in Progress 2/24/2023 JAVIER RAMOS JR
Permit Finaled 3/7/2023 MICHAEL SMITH
CofO Issued 3/7/2023 MICHAEL SMITH
Permit Finaled 3/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/8/2021 CARLOS AGUILERA
Sewer availability Cleared 11/8/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/17/2021 GILBERT URREA
Roof/Waste drainage to street Cleared 1/6/2022 CARLOS AGUILERA
GPI Written Notices Cleared 1/13/2022 SELLA BENYAMIN
Grading Pre-Inspection Cleared 1/13/2022 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/9/2022 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/11/2022 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 2/18/2022 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 2/18/2022 Partial Approval MICHAEL TEMPLE
Sewer 2/18/2022 Approved MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 3/16/2022 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 3/29/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 3/29/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/7/2022 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 6/21/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 6/21/2022 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 6/21/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/21/2022 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 6/24/2022 Conditional Approval DEANDRE HOFFMAN
ELECTRICAL-Rough 6/27/2022 Approved JAVIER RAMOS JR
HVAC-Rough 6/27/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/27/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/19/2022 No Access for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 No Access for Inspection JAVIER RAMOS JR
Green Building Rough 7/19/2022 No Access for Inspection JAVIER RAMOS JR
Shower Pan 7/28/2022 Approved ROBERT GOLD
Special/Order Compliance 7/28/2022 Approved ROBERT GOLD
BUILDING-Rough-Frame 8/11/2022 Partial Approval JAVIER RAMOS JR
Drywall Nailing 8/11/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/11/2022 Approved JAVIER RAMOS JR
Green Building Rough 8/11/2022 Approved JAVIER RAMOS JR
Insulation 8/11/2022 Approved JAVIER RAMOS JR
Drywall Nailing 8/29/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/29/2022 Approved JAVIER RAMOS JR
Underground Mechanical 9/19/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/7/2023 Approved JAVIER RAMOS JR
Final 2/7/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/7/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/7/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/7/2023 Approved JAVIER RAMOS JR
Final 2/24/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 2/24/2023 Approved JAVIER RAMOS JR