7669 N BEEMAN AVE 1-2 91605

Certificate Information: 7669 N BEEMAN AVE 1-2 91605

Application / Permit
21014-20000-03957
Plan Check / Job No.
B21VN10397
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18' 6" X 37' REAR ADDITION TO (E) SFD TO EXTEND DINING ROOM, ADD MASTER BEDROOM/BATHROOM/CLOSET/OFFICE AND CONVERT ATTACHED 17' 10" X 20' 7" GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 8/12/2021 GURUNATH NESARAJAH
Corrections Issued 8/14/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/6/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 5/21/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 6/6/2022 GURUNATH NESARAJAH
Plan Check Approved 6/21/2022 GURUNATH NESARAJAH
Building Plans Picked Up 6/24/2022 APPLICANT
Issued 7/18/2022 APPLICANT
CofO in Progress 7/30/2025 VINCENT HANLEY
Permit Finaled 8/19/2025 RUBEN SALAS
CofO Issued 8/19/2025 RUBEN SALAS
Permit Finaled 8/19/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/22/2021 RIDWAN HARDY
Address approval Cleared 3/7/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/8/2022 CARLOS AGUILERA
Sewer availability Cleared 3/8/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/7/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 1/10/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Approved VINCENT HANLEY
Gas Test 1/16/2025 Approved VINCENT HANLEY
HVAC-Rough 1/16/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/16/2025 Approved VINCENT HANLEY
Sewer 1/16/2025 Approved VINCENT HANLEY
Deputy Wood Construction 1/17/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/23/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved VINCENT HANLEY
HVAC-Rough 1/23/2025 Corrections Issued VINCENT HANLEY
HVAC-Rough 2/12/2025 Partial Approval MATTHEW NELSON
Wood Frame 2/12/2025 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 2/13/2025 Approved VINCENT HANLEY
Green Building Rough 2/13/2025 Approved VINCENT HANLEY
HVAC-Rough 2/13/2025 Approved VINCENT HANLEY
MERV13>=Rough 2/13/2025 Approved VINCENT HANLEY
Wood Frame 2/13/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/19/2025 No Access for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 2/20/2025 Partial Approval MICHAEL CORTEZ
Interior/Exterior Lathing 2/21/2025 No Access for Inspection MISAEL ESPARZA
Insulation 2/25/2025 Approved RYAN SALAZAR
Shower Pan 2/25/2025 Approved RYAN SALAZAR
Drywall Nailing 3/3/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/3/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/15/2025 Corrections Issued MISAEL ESPARZA
Final 7/15/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 7/15/2025 Partial Inspection MISAEL ESPARZA
Gas Test 7/15/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 7/15/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 7/15/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Final 7/15/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 7/15/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 7/15/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 7/15/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 7/22/2025 Approved VINCENT HANLEY
Final 7/22/2025 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 7/22/2025 Approved VINCENT HANLEY
Gas Test 7/22/2025 Approved VINCENT HANLEY
Green Building Final 7/22/2025 Approved VINCENT HANLEY
HVAC-Final 7/22/2025 Approved VINCENT HANLEY
MERV13>=Final 7/22/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/22/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 7/22/2025 Approved VINCENT HANLEY
Smoke Detectors 7/22/2025 Approved VINCENT HANLEY
Final 7/29/2025 OK to Issue CofO VINCENT HANLEY