11314 W BLYTHE ST 91352
Certificate Information: 11314 W BLYTHE ST 91352
- Application / Permit
- 21014-20000-03948
- Plan Check / Job No.
- B21VN10349
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (25'-0"x24'-0"), 467 SQFT ADDITION AT THE FRONT OF THE (E) SFD.
- Permit Issued
- Issued on 12/13/2021
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | PETER MOSESIAN |
| Corrections Issued | 8/5/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| Issued | 12/13/2021 | APPLICANT |
| CofO in Progress | 8/30/2023 | WILLIAM WREN |
| CofO Issued | 9/18/2023 | RUBEN SALAS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/16/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/18/2022 | Partial Approval | MATT KELLERMAN |
| Interior/Exterior Lathing | 2/18/2022 | Partial Approval | MATT KELLERMAN |
| Wood Frame | 2/18/2022 | Corrections Issued | MATT KELLERMAN |
| Deputy Wood Construction | 3/1/2022 | No Result Entered | ADRIAN GAUTHIER |
| BUILDING-Rough-Frame | 3/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| FLOOD-Proofing Certificate | 3/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 3/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/14/2022 | Approved | RYAN SALAZAR |
| Insulation | 3/14/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 3/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/22/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 5/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 8/29/2023 | OK to Issue CofO | WILLIAM WREN |