3741 S VIRGINIA ROAD 90016
Certificate Information: 3741 S VIRGINIA ROAD 90016
- Application / Permit
- 21014-20000-03922
- Plan Check / Job No.
- B21VN10298
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 18'X19' GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 7'X19' ADDITION. ALL WORK PER ENGR. SEE COMMENTS.
- Permit Issued
- Issued on 10/29/2021
- Issuing Office
- Current Status
- CofO Issued on 2/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 8/15/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 10/29/2021 | HAYATO TSUCHIYA |
| Issued | 10/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/1/2021 | APPLICANT |
| CofO in Progress | 1/25/2023 | ANTHONY EGSON |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
| CofO Issued | 2/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 8/21/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/23/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 10/20/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/20/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2021 | RENZ SORIANO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | South Land Remodeling Inc; Lic. No.: 901842-B | 10770 DES MOINES AVE NORTHRIDGE, CA 91326 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/10/2022 | Corrections Issued | ANTHONY EGSON |
| Sewer | 1/10/2022 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/10/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 1/18/2022 | Approved | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 2/8/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 2/22/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 2/24/2022 | Approved | HORACE FULTZ |
| BUILDING-Rough-Frame | 4/12/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/12/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/12/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/12/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/20/2022 | Corrections Issued | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 4/20/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 5/4/2022 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/13/2022 | Partial Approval | HORACE FULTZ |
| Shower Pan | 5/13/2022 | Approved | HORACE FULTZ |
| Insulation | 5/17/2022 | Approved | HORACE FULTZ |
| Drywall Nailing | 5/20/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/20/2022 | Approved | ANTHONY EGSON |
| Sewer | 5/31/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 7/25/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 7/25/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 7/25/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 7/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 7/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 7/29/2022 | Partial Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 8/5/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 8/10/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/10/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/10/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/19/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 8/19/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 8/19/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 8/19/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 8/19/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/24/2022 | Approved | ANTHONY EGSON |
| Final | 8/24/2022 | Partial Approval | ANTHONY EGSON |
| Final | 1/25/2023 | OK to Issue CofO | ANTHONY EGSON |