3741 S VIRGINIA ROAD 90016

Certificate Information: 3741 S VIRGINIA ROAD 90016

Application / Permit
21014-20000-03922
Plan Check / Job No.
B21VN10298
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED 18'X19' GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH 7'X19' ADDITION. ALL WORK PER ENGR. SEE COMMENTS.
Permit Issued
Issued on 10/29/2021
Issuing Office
Current Status
CofO Issued on 2/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 HAYATO TSUCHIYA
Corrections Issued 8/15/2021 HAYATO TSUCHIYA
Plan Check Approved 10/29/2021 HAYATO TSUCHIYA
Issued 10/29/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 1/25/2023 ANTHONY EGSON
Permit Finaled 2/11/2023 DANIEL ORRANTE
CofO Issued 2/11/2023 DANIEL ORRANTE
Permit Finaled 2/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/21/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/21/2021 RENZ SORIANO
Sewer availability Cleared 8/23/2021 RENZ SORIANO
Construction near power lines Cleared 10/20/2021 RIDWAN HARDY
Construction within easement Cleared 10/20/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/21/2021 RENZ SORIANO

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor South Land Remodeling Inc; Lic. No.: 901842-B 10770 DES MOINES AVE      NORTHRIDGE, CA 91326

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/10/2022 Corrections Issued ANTHONY EGSON
Sewer 1/10/2022 Corrections Issued ANTHONY EGSON
Underground Mechanical 1/10/2022 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 1/18/2022 Approved ANTHONY EGSON
Deputy Drilled-In Anchors 2/8/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 2/8/2022 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 2/22/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 2/24/2022 Approved HORACE FULTZ
BUILDING-Rough-Frame 4/12/2022 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 4/12/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 4/12/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 4/12/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/20/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 4/20/2022 Corrections Issued ANTHONY EGSON
Rough-Elec/Plmb/HVAC 4/20/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Approved ANTHONY EGSON
Deputy Wood Construction 5/4/2022 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 5/13/2022 Partial Approval HORACE FULTZ
Shower Pan 5/13/2022 Approved HORACE FULTZ
Insulation 5/17/2022 Approved HORACE FULTZ
Drywall Nailing 5/20/2022 Approved ANTHONY EGSON
Green Building Rough 5/20/2022 Approved ANTHONY EGSON
Sewer 5/31/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/25/2022 Not Ready for Inspection ANTHONY EGSON
Final 7/25/2022 Corrections Issued ANTHONY EGSON
Green Building Final 7/25/2022 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/25/2022 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 7/25/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 7/29/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 7/29/2022 Partial Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/5/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 8/5/2022 Not Ready for Inspection ANTHONY EGSON
Final 8/5/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 8/5/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 8/5/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 8/5/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 8/10/2022 Corrections Issued ANTHONY EGSON
HVAC-Final 8/10/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 8/10/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 8/19/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 8/19/2022 Corrections Issued ANTHONY EGSON
Final 8/19/2022 Corrections Issued ANTHONY EGSON
Green Building Final 8/19/2022 Approved ANTHONY EGSON
HVAC-Final 8/19/2022 Approved ANTHONY EGSON
PLUMBING-Final 8/19/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 8/24/2022 Approved ANTHONY EGSON
Final 8/24/2022 Partial Approval ANTHONY EGSON
Final 1/25/2023 OK to Issue CofO ANTHONY EGSON