2457 N SUNDOWN DR 90065
Certificate Information: 2457 N SUNDOWN DR 90065
- Application / Permit
- 21014-20000-03908
- Plan Check / Job No.
- B21VN10264
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF (E) SFD W/ROOFTOP DECK ABOVE. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 9/6/2021 | GURUNATH NESARAJAH |
| Quality Review Completed | 9/8/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/10/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 6/22/2023 | GURUNATH NESARAJAH |
| Issued | 4/15/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | THOMAS LOGRASSO |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
| CofO Issued | 2/13/2025 | DEROLD HAUFF |
| Permit Finaled | 2/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/4/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2021 | WALLIE JONG |
| ZA Case | Cleared | 10/5/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 10/5/2021 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | WALLIE JONG |
| Specific Plan | Cleared | 6/7/2023 | DAVID URITA |
Contact Information
| Architect | Neilson,, Jeffrey William; Lic. No.: C36101 | 2456 SUNDOWN DRIVE LOS ANGELES, CA 90065 |
| Contractor | M Librush Construction Inc; Lic. No.: 933238-B | 541 SOUTH SPRING ST STE 213 LOS ANGELES, CA 90013 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/14/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/14/2024 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/16/2024 | Approved | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 5/22/2024 | Conditional Approval | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 5/23/2024 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 5/23/2024 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2024 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 7/16/2024 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/13/2024 | Conditional Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/13/2024 | Approved | THOMAS LOGRASSO |
| Shower Pan | 8/13/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 8/13/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 8/28/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/28/2024 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 8/28/2024 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/11/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/14/2025 | Approved | THOMAS LOGRASSO |
| Final | 1/14/2025 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 1/14/2025 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 1/14/2025 | Approved | THOMAS LOGRASSO |
| Final | 1/28/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 1/28/2025 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 2/10/2025 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Approved | THOMAS LOGRASSO |