12120-12122 N RAHN AVE 91344
Certificate Information: 12120-12122 N RAHN AVE 91344
- Application / Permit
- 21014-20000-03861
- Plan Check / Job No.
- B21VN10081
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan Check* CONVERT EXISTING GARAGE TO ADU PER GCS 65852.2(e)(1)(A) AND PER WFPP
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 8/6/2021 | APPLICANT |
Assigned to Plan Check Engineer | 8/8/2021 | CRYSTEL MAALOUF |
Corrections Issued | 8/10/2021 | CRYSTEL MAALOUF |
Applicant returned to address corrections | 9/16/2021 | CRYSTEL MAALOUF |
Plan Check Approved | 9/17/2021 | CRYSTEL MAALOUF |
Issued | 9/27/2021 | APPLICANT |
CofO in Progress | 1/19/2023 | JAVIER RAMOS JR |
CofO Issued | 2/17/2023 | MICHAEL SMITH |
Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
Address approval | Cleared | 8/18/2021 | GABRIEL ROBLES |
Sewer availability | Cleared | 8/18/2021 | GABRIEL ROBLES |
Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | GABRIEL ROBLES |
Grading Pre-Inspection | Cleared | 9/1/2021 | PATRICK MISCHLICH |
Contact Information
Contractor | Owner-Builder | , |
Inspector Information
CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
NICHOLAS TROWBRIDGE, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 5/25/2022 | Approved | JAVIER RAMOS JR |
Footing/Foundation/Slab | 7/25/2022 | Approved | DEANDRE HOFFMAN |
PLUMBING-Rough | 7/25/2022 | Partial Approval | DEANDRE HOFFMAN |
Gas Test | 8/11/2022 | Approved | DEANDRE HOFFMAN |
PLUMBING-Rough | 8/11/2022 | Partial Approval | DEANDRE HOFFMAN |
Sewer | 8/11/2022 | Approved | DEANDRE HOFFMAN |
Wood Frame | 8/11/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
ELECTRICAL-Rough | 9/20/2022 | Approved | JAVIER RAMOS JR |
Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | JAVIER RAMOS JR |
HVAC-Rough | 10/19/2022 | Approved | JAVIER RAMOS JR |
Insulation | 10/19/2022 | Partial Approval | JAVIER RAMOS JR |
Insulation | 10/26/2022 | Partial Approval | THOMAS FINNILA |
Interior/Exterior Lathing | 10/26/2022 | Corrections Issued | THOMAS FINNILA |
Insulation | 11/2/2022 | Approved | JAVIER RAMOS JR |
Interior/Exterior Lathing | 11/2/2022 | Approved | JAVIER RAMOS JR |
Drywall Nailing | 11/14/2022 | Approved | ROBERT GOLD |
Shower Pan | 11/14/2022 | Approved | ROBERT GOLD |
BUILDING-Rough-Frame | 1/5/2023 | Partial Inspection | MICHEL ABAJAN |
ELECTRICAL-Final | 1/5/2023 | Approved | MICHEL ABAJAN |
Final | 1/5/2023 | Corrections Issued | MICHEL ABAJAN |
Gas Test | 1/5/2023 | Approved | MICHEL ABAJAN |
Green Building Final | 1/5/2023 | Not Ready for Inspection | MICHEL ABAJAN |
Green Building Rough | 1/5/2023 | Partial Inspection | MICHEL ABAJAN |
HVAC-Final | 1/5/2023 | Approved | MICHEL ABAJAN |
PLUMBING-Final | 1/5/2023 | Approved | MICHEL ABAJAN |
SGSOV-Seismic Gas S/O Valve | 1/5/2023 | SGSOV Approved | MICHEL ABAJAN |
Smoke Detectors | 1/5/2023 | Approved | MICHEL ABAJAN |
BUILDING-Rough-Frame | 1/18/2023 | Approved | JAVIER RAMOS JR |
Final | 1/18/2023 | OK to Issue CofO | JAVIER RAMOS JR |
Green Building Final | 1/18/2023 | Approved | JAVIER RAMOS JR |
Green Building Rough | 1/18/2023 | Approved | JAVIER RAMOS JR |