1946 1/2-3/4 N PRESTON AVE 90026

Certificate Information: 1946 1/2-3/4 N PRESTON AVE 90026

Application / Permit
21014-20000-03852
Plan Check / Job No.
B21VN10028
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT (E) CRAWL SPACE INTO (N) 1-BEDROOM UNIT; CONVERT (E) 1-BEDROOM UNIT TO 2-BEDROOM UNIT AT LOWER LEVEL UNIT OF (E) 3-UNIT APT BLDG CREATING A 4-UNIT APT BLDG
Permit Issued
Issued on 1/4/2022
Issuing Office
Current Status
CofO Corrected on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 NILOOFAR MEHRAIN
Corrections Issued 9/7/2021 NILOOFAR MEHRAIN
Quality Review Completed 9/14/2021 STEVEN KIM
Building Plans Picked Up 9/17/2021 APPLICANT
Applicant returned to address corrections 12/16/2021 NILOOFAR MEHRAIN
Plan Check Approved 12/29/2021 NILOOFAR MEHRAIN
Issued 1/4/2022 APPLICANT
CofO in Progress 3/4/2024 RONALD JIMENEZ
CofO Issued-Status Void 3/6/2024 ERNESTO CORRAL
Permit Finaled-Status Void 3/6/2024 ERNESTO CORRAL
Re-Activate Permit 3/29/2024 ERNESTO CORRAL
Permit Finaled 3/29/2024 ERNESTO CORRAL
CofO Corrected 3/29/2024 ERNESTO CORRAL
Permit Finaled 3/29/2024 ERNESTO CORRAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/5/2021 NILOOFAR MEHRAIN
Sewer availability Cleared 11/15/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/18/2021 STEVE MELGAR
Address approval Cleared 11/22/2021 STEVE MELGAR
Hydrant and Access approval Cleared 12/17/2021 MATTHEW CRAIG
Green Code Cleared 12/30/2021 MICHAEL AYERS

Contact Information

Contractor Aiden'S Structural Concepts; Lic. No.: 922303-B 13230 BROMONT AVE #111      SYLMAR, CA 91342
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 12/1/2022 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 12/2/2022 Not Ready for Inspection RAFAEL CORTES
Grading Pre-Inspection 12/2/2022 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 12/6/2022 Corrections Issued MARK FERRARI
Deputy Shotcrete 12/8/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 12/22/2022 Partial Approval RAFAEL CORTES
Deputy Shotcrete 1/10/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 5/11/2023 Partial Approval JULIAN CAPUCETTI
Wood Frame 5/11/2023 Partial Approval JULIAN CAPUCETTI
Green Building Rough 6/1/2023 Approved JULIAN CAPUCETTI
Wood Frame 6/1/2023 Approved JULIAN CAPUCETTI
Interior/Exterior Lathing 6/8/2023 Partial Approval ALFREDO LOPEZ
Interior/Exterior Lathing 6/9/2023 Approved JULIAN CAPUCETTI
Insulation 6/16/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 6/26/2023 Approved JULIAN CAPUCETTI
Final 1/12/2024 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 1/12/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 1/12/2024 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 1/12/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 1/24/2024 Corrections Issued RONALD JIMENEZ
Footing/Foundation/Slab 1/24/2024 Approved RONALD JIMENEZ
Green Building Final 1/24/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Not Ready RONALD JIMENEZ
Smoke Detectors 1/24/2024 Not Ready for Inspection RONALD JIMENEZ
Final 1/31/2024 Partial Approval RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 1/31/2024 Approved RONALD JIMENEZ
Final 3/4/2024 OK to Issue CofO RONALD JIMENEZ