2839 N PACIFIC VIEW TR 90068

Certificate Information: 2839 N PACIFIC VIEW TR 90068

Application / Permit
21014-20000-03840
Plan Check / Job No.
B21VN09998
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'11"X40'0" IRREGULAR SHAPED LOWER LEVEL ADDITION AND INTERIOR REMODEL TO THE (E) SFD
Permit Issued
Issued on 1/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 MARVEL DELACRUZ
Corrections Issued 9/16/2021 MARVEL DELACRUZ
Quality Review Completed 9/22/2021 STEVEN KIM
Building Plans Picked Up 9/29/2021 APPLICANT
Applicant returned to address corrections 3/4/2022 MARVEL DELACRUZ
Applicant returned to address corrections 3/31/2022 RAPHAEL ROSAS
Applicant returned to address corrections 12/9/2022 MARVEL DELACRUZ
Applicant returned to address corrections 1/12/2023 MARVEL DELACRUZ
Plan Check Approved 1/12/2023 MARVEL DELACRUZ
Issued 1/12/2023 APPLICANT
CofO in Progress 9/9/2024 BRIAN SULLIVAN
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 11/4/2021 OLGA AYALA
ZI Cleared 11/4/2021 OLGA AYALA
Distance to fire station Cleared 4/14/2022 KURT CORRAL
Hydrant and Access approval Cleared 4/14/2022 KURT CORRAL
Private sewage disp. approval Cleared 5/10/2022 STEVEN KIM
BHO/Hillside ordinance Cleared 12/8/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/8/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 12/8/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 12/8/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 12/9/2022 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 12/9/2022 MARVEL DELACRUZ
Green Code Cleared 12/9/2022 MARVEL DELACRUZ
Roof/Waste drainage to street Cleared 12/12/2022 COLIN LOREDO
Miscellaneous Cleared 12/16/2022 DANIEL CORONADO
Miscellaneous Cleared 12/16/2022 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406
Engineer Masterman,, Gary Clyde; Lic. No.: GE567 1766 EAGLE RIDGE CIR      WICHITA FALLS, TX 76309
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/28/2023 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/23/2023 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 3/28/2023 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 5/1/2023 Approved BRIAN SULLIVAN
PLUMBING-Rough 7/31/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 10/31/2023 Approved BRIAN SULLIVAN
Wood Frame 10/31/2023 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 11/1/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 11/2/2023 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 11/29/2023 Approved BRIAN SULLIVAN
HVAC-Rough 11/29/2023 Corrections Issued BRIAN SULLIVAN
Wood Frame 11/29/2023 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/15/2023 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 12/15/2023 Approved SCOTT FINNILA
Green Building Rough 12/15/2023 Approved SCOTT FINNILA
HVAC-Rough 12/15/2023 Approved SCOTT FINNILA
Insulation 1/2/2024 Partial Approval ROY SPAULDING
Drywall Nailing 2/21/2024 Approved ROY SPAULDING
Shower Pan 4/10/2024 Corrections Issued BRIAN SULLIVAN
Shower Pan 4/12/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/17/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 6/14/2024 Approved BRIAN SULLIVAN
PLUMBING-Final 8/6/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/23/2024 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/23/2024 Approved BRIAN SULLIVAN
Final 8/23/2024 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 8/23/2024 Approved BRIAN SULLIVAN
Green Building Final 8/23/2024 Approved BRIAN SULLIVAN
HVAC-Final 8/23/2024 Conditional Approval BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 8/23/2024 Corrections Issued BRIAN SULLIVAN
Final 8/27/2024 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 8/27/2024 Approved BRIAN SULLIVAN
Final 9/6/2024 OK to Issue CofO BRIAN SULLIVAN