9430 N PETIT AVE 91343

Certificate Information: 9430 N PETIT AVE 91343

Application / Permit
21014-20000-03824
Plan Check / Job No.
B21VN09898
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 118.5 SF TO THE (E) SFD AND INTERIOR REMODEL. ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/20/2021
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 LUISANGEL VALENZUELA
Corrections Issued 7/29/2021 LUISANGEL VALENZUELA
Plan Check Approved 9/16/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 9/23/2021 APPLICANT
Issued 12/20/2021 APPLICANT
CofO in Progress 7/15/2025 NICHOLAS TROWBRIDGE
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/26/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/26/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 9/7/2021 TIMOTHY POWELL

Contact Information

Contractor Prime Builders Construction Co; Lic. No.: 953200-B 10349 DENSMORE AVENUE      GRANADA HILLS, CA 91344
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 3/24/2022 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 5/4/2022 Approved ALAN MORELOS
HVAC-Rough 5/4/2022 Approved ALAN MORELOS
PLUMBING-Rough 5/4/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Approved ALAN MORELOS
Wood Frame 5/10/2022 Approved ALAN MORELOS
Drywall Nailing 5/17/2022 Partial Inspection RAUL OLAGI
Insulation 5/17/2022 Partial Inspection RAUL OLAGI
Interior/Exterior Lathing 5/23/2022 Approved ALAN MORELOS
Shower Pan 5/23/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 7/20/2023 Not Ready for Inspection JUAN VALENZUELA
Drywall Nailing 7/20/2023 Not Ready for Inspection JUAN VALENZUELA
Final 7/20/2023 Corrections Issued JUAN VALENZUELA
Green Building Final 7/20/2023 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 7/20/2023 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 7/20/2023 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 7/20/2023 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 10/2/2023 Approved RAUL OLAGI
Drywall Nailing 10/2/2023 Approved RAUL OLAGI
Final 10/2/2023 Corrections Issued RAUL OLAGI
Green Building Final 10/2/2023 Approved RAUL OLAGI
Green Building Rough 10/2/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 10/2/2023 Approved RAUL OLAGI
Final 1/22/2025 Corrections Issued SALVADOR MARTINEZ
Final 7/14/2025 OK to Issue CofO NICHOLAS TROWBRIDGE