7030 N SAUSALITO AVE 91307

Certificate Information: 7030 N SAUSALITO AVE 91307

Application / Permit
21014-20000-03820
Plan Check / Job No.
B21VN09892
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF AN ATTACHED PATIO COVER PER IB P/BC 2020-006 WITH CEILING FAN.
Permit Issued
Issued on 12/14/2021
Issuing Office
Current Status
CofO Issued on 6/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 8/16/2021 COLIN LOREDO
Corrections Issued 8/16/2021 COLIN LOREDO
Building Plans Picked Up 11/24/2021 APPLICANT
Plan Check Approved 12/7/2021 COLIN LOREDO
Issued 12/14/2021 APPLICANT
CofO in Progress 5/19/2022 CHRIS CHRISTENSEN
Permit Finaled 6/2/2022 MICHAEL SMITH
CofO Issued 6/2/2022 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 11/18/2021 MIGUEL GAMBOA
ZA Case Cleared 11/18/2021 MIGUEL GAMBOA
ZA Case Cleared 11/18/2021 MIGUEL GAMBOA
ZA Case Cleared 11/18/2021 MIGUEL GAMBOA
ZA Case Cleared 11/18/2021 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 11/29/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/30/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/28/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/10/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/10/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 5/18/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/18/2022 Approved CHRIS CHRISTENSEN
Final 5/18/2022 OK to Issue CofO CHRIS CHRISTENSEN
Smoke Detectors 5/18/2022 Approved CHRIS CHRISTENSEN