10659 N SABLE AVE 91040

Certificate Information: 10659 N SABLE AVE 91040

Application / Permit
21014-20000-03803
Plan Check / Job No.
B21VN09855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 24'-6" x 14'-0" SECOND STORY ADDITION TO AND CONVERT THE (E) ATT. GARAGE INTO A NEW (602 S.F) ACCESSORY DWELLING UNIT WITH 4'-0" x 11'-0" BALCONY PER LAMC 12.22 A.33 (c)-(d). NEW RETAINING WALL TO SUPPORT SECOND STORY ADDITION " NFPA 13-D FIRE SPRINKLERS THRU-OUT ".
Permit Issued
Issued on 5/12/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 9/2/2021 SARKIS HARABEDIAN
Corrections Issued 9/7/2021 SARKIS HARABEDIAN
Quality Review Completed 9/9/2021 STEVEN KIM
Applicant returned to address corrections 3/22/2022 SARKIS HARABEDIAN
Building Plans Picked Up 4/28/2022 APPLICANT
Applicant returned to address corrections 8/26/2022 SARKIS HARABEDIAN
Plan Check Approved 11/21/2022 SARKIS HARABEDIAN
Issued 5/12/2023 APPLICANT
CofO in Progress 5/6/2024 WILLIAM WREN
Permit Finaled 5/10/2024 RUBEN SALAS
CofO Issued 5/10/2024 RUBEN SALAS
Permit Finaled 5/10/2024 RUBEN SALAS

Permit Application Clearance Information

GPI Written Notices Cleared 9/6/2021 SARKIS HARABEDIAN
Grading Pre-Inspection Cleared 9/6/2021 SARKIS HARABEDIAN
Address approval Cleared 1/19/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 1/19/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 1/19/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 1/19/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 1/19/2022 JOSE DUARTE-DIAZ
BHO/Hillside ordinance Cleared 1/19/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 1/19/2022 JOSE DUARTE-DIAZ
Street Frontage Cleared 1/19/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/1/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/1/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 6/10/2022 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311
Engineer Molai,, Mohamad Ali; Lic. No.: L9192 24308 BURBANK BLVD      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/11/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 8/23/2023 Approved WILLIAM WREN
PLUMBING-Rough 8/23/2023 Partial Approval WILLIAM WREN
Masonry Wall/Backfill 8/28/2023 Approved WILLIAM WREN
Reinforced Masonry Frame 8/28/2023 Approved WILLIAM WREN
Footing/Foundation/Slab 9/13/2023 Approved WILLIAM WREN
Pre-Inspection 9/13/2023 Not Ready for Inspection WILLIAM WREN
Pre-Inspection 9/18/2023 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Corrections Issued WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/30/2023 Partial Approval WILLIAM WREN
Underground Mechanical 10/30/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Not Ready for Inspection WILLIAM WREN
Gas Test 11/8/2023 Approved WILLIAM WREN
HVAC-Rough 11/8/2023 Approved WILLIAM WREN
PLUMBING-Rough 11/8/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/15/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 11/15/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/15/2023 Not Ready for Inspection DAVID ANDERSON
Green Building Rough 11/15/2023 Approved DAVID ANDERSON
Sewer 11/15/2023 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/15/2023 Corrections Issued DAVID ANDERSON
Deputy Wood Construction 11/17/2023 Conditional Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Approved WILLIAM WREN
Wood Frame 11/21/2023 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 11/22/2023 Approved WILLIAM WREN
Verify Sprinkler Sign Off 11/22/2023 Approved WILLIAM WREN
Insulation 12/4/2023 Corrections Issued WILLIAM WREN
Drywall Nailing 12/14/2023 Approved WILLIAM WREN
Drywall Nailing 12/20/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 1/17/2024 Approved WILLIAM WREN
Shower Pan 1/17/2024 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 1/23/2024 Approved RUBEN SALAS
Gas Test 2/15/2024 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 2/15/2024 Not Ready for Inspection WILLIAM WREN
Shower Pan 2/15/2024 Approved WILLIAM WREN
Final 3/18/2024 Corrections Issued WILLIAM WREN
Green Building Final 3/18/2024 Not Ready for Inspection WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 3/18/2024 Not Ready for Inspection WILLIAM WREN
Final 4/8/2024 OK to Issue CofO WILLIAM WREN
Green Building Final 4/8/2024 Approved WILLIAM WREN
Smoke Detectors 4/8/2024 Approved WILLIAM WREN