19114-19116 W ERWIN ST 91335
Certificate Information: 19114-19116 W ERWIN ST 91335
- Application / Permit
- 21014-20000-03802
- Plan Check / Job No.
- B21VN09854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTATCHED GARAGE INTO ADU W/2-STORY ADDITION (26'-2"x20'-1") AND A 1ST FLOOR ADDITION (4'-0"x20'-1") PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 9/30/2021
- Issuing Office
- Current Status
- CofO Issued on 12/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | PETER MOSESIAN |
| Corrections Issued | 9/5/2021 | PETER MOSESIAN |
| Quality Review Completed | 9/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| Plan Check Approved | 9/30/2021 | PETER MOSESIAN |
| Issued | 9/30/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | SEAN HAUPT |
| CofO in Progress | 9/29/2022 | SEAN HAUPT |
| CofO Issued | 12/9/2022 | MICHAEL SMITH |
| Permit Finaled | 12/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/10/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/21/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/21/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/21/2021 | Partial Approval | SEAN HAUPT |
| Footing/Foundation/Slab | 12/28/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 1/18/2022 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/4/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 3/4/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/4/2022 | Approved | SEAN HAUPT |
| Wood Frame | 3/4/2022 | Corrections Issued | SEAN HAUPT |
| Interior/Exterior Lathing | 3/10/2022 | Approved | SEAN HAUPT |
| Insulation | 3/17/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 4/4/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 4/4/2022 | Approved | VINCENT HANLEY |
| Shower Pan | 4/26/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | SEAN HAUPT |
| Final | 9/16/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 9/16/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 9/16/2022 | Approved | SEAN HAUPT |
| Final | 9/28/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 9/28/2022 | Approved | SEAN HAUPT |