11977-11981 W PIERCE ST 91342
Certificate Information: 11977-11981 W PIERCE ST 91342
- Application / Permit
- 21014-20000-03800
- Plan Check / Job No.
- B21VN09853
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT. GARAGE TO JUNIOR ACCESSORY DWELLING AND ADD 20'-10" x 20'-10" NEW 2ND FLR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 5852.22 AND LAMC 12.22 A.33(c) and (e); ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | SEAN SHAHMIRI |
| Corrections Issued | 8/31/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 9/8/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Plan Check Approved | 10/12/2021 | SEAN SHAHMIRI |
| Issued | 10/12/2021 | APPLICANT |
| CofO in Progress | 4/5/2023 | MICHEL ABAJAN |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
| CofO Issued | 4/6/2023 | MICHAEL SMITH |
| Permit Finaled | 4/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/30/2021 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 8/30/2021 | LAUREN PADICK |
| Roof/Waste drainage to street | Cleared | 8/30/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/7/2021 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 9/20/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2022 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 5/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 6/9/2022 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 8/5/2022 | Partial Approval | MICHEL ABAJAN |
| Sewer | 8/5/2022 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 9/14/2022 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/14/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/16/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 9/16/2022 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/26/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/26/2022 | Approved | MICHEL ABAJAN |
| Insulation | 9/26/2022 | Partial Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/26/2022 | Approved | MICHEL ABAJAN |
| Insulation | 9/27/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/29/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/25/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| Final | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/21/2023 | Approved | MICHEL ABAJAN |
| Green Building Final | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/21/2023 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| Final | 4/5/2023 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/5/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/5/2023 | Approved | MICHEL ABAJAN |