2203 N NOTTINGHAM AVE 90027
Certificate Information: 2203 N NOTTINGHAM AVE 90027
- Application / Permit
- 21014-20000-03779
- Plan Check / Job No.
- B21VN09807
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING SINGLE FAMILY DWELLING; ENCLOSE EXISTING BREEZEWAY AND CONVERT EXISTING ATTIC AS PART OF DWELLING; INTERIOR REMODEL
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 8/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | SELLA BENYAMIN |
| Corrections Issued | 9/2/2021 | SELLA BENYAMIN |
| Quality Review Completed | 9/9/2021 | STEVEN KIM |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Plan Check Approved | 10/18/2021 | SELLA BENYAMIN |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 8/8/2023 | STUART CHAPMAN |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
| CofO Issued | 8/8/2023 | DEROLD HAUFF |
| Permit Finaled | 8/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 9/15/2021 | DANIEL CORONADO |
| Miscellaneous | Cleared | 9/15/2021 | DANIEL CORONADO |
| BHO/Hillside ordinance | Cleared | 9/18/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2021 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 9/20/2021 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 9/20/2021 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 9/20/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/20/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Louis & Rose Construction Corp; Lic. No.: 1073934-B | 8033 SUNSET BLVD LOS ANGELES, CA 90046 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2021 | Conditional Approval | ADAM ESCOTO |
| Footing/Foundation/Slab | 1/4/2022 | Approved | RAUL BARAJAS |
| Deputy Steel/Welding | 6/24/2022 | Conditional Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/15/2022 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/15/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 8/15/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 8/15/2022 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/15/2022 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/22/2022 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/22/2022 | Approved | BRIAN SULLIVAN |
| Wood Frame | 8/22/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Wood Construction | 8/24/2022 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/2/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 9/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 9/14/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/20/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Wood Frame | 9/20/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 10/25/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 10/25/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Wood Frame | 10/25/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Shower Pan | 10/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 11/8/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Shower Pan | 11/8/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/15/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 11/15/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 11/15/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/23/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/29/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 1/17/2023 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/22/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 7/22/2023 | Approved | RAUL BARAJAS |
| Final | 7/22/2023 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 7/22/2023 | Approved | RAUL BARAJAS |
| HVAC-Final | 7/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 7/22/2023 | Partial Approval | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 7/22/2023 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 7/22/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 7/27/2023 | Approved | STUART CHAPMAN |
| Final | 7/27/2023 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 7/27/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 7/27/2023 | Approved | STUART CHAPMAN |
| Final | 8/8/2023 | OK to Issue CofO | STUART CHAPMAN |