14003 W LAKESIDE ST 91342
Certificate Information: 14003 W LAKESIDE ST 91342
- Application / Permit
- 21014-20000-03766
- Plan Check / Job No.
- B21VN09739
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'-6" X 16'-10" ADDITION OF TWO BEDROOMS AND ONE BATHROOM TO THE (E) SFD. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 1/10/2022
- Issuing Office
- Current Status
- CofO Issued on 7/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2021 | PARISA ZAHABI |
| Corrections Issued | 7/27/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/19/2021 | PARISA ZAHABI |
| Plan Check Approved | 8/30/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 9/1/2021 | APPLICANT |
| Issued | 1/10/2022 | APPLICANT |
| CofO in Progress | 6/10/2022 | JOHN HAYES |
| Permit Finaled | 7/12/2022 | MICHAEL SMITH |
| CofO Issued | 7/12/2022 | MICHAEL SMITH |
| Permit Finaled | 7/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/3/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 8/3/2021 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 8/3/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/9/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Sharp Builders; Lic. No.: 950190-B | 8432 SHARP AVENUE SUN VALLEY, CA 91352 |
| Engineer | Santos,, Michael Fernandez; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/13/2022 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 1/18/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/4/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | JOHN HAYES |
| Green Building Rough | 2/4/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/14/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 2/14/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/24/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 2/24/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/24/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/24/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/24/2022 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 2/24/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 3/3/2022 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/3/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/11/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | JOHN HAYES |
| Green Building Rough | 3/29/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/29/2022 | Approved | JOHN HAYES |
| Insulation | 4/1/2022 | Approved | JOHN HAYES |
| Shower Pan | 4/1/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 4/6/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/6/2022 | Approved | JOHN HAYES |
| Final | 5/12/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/12/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/26/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/26/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/26/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/26/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/9/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 6/9/2022 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 6/9/2022 | Approved | JOHN HAYES |