10545 N HAYVENHURST AVE 91344
Certificate Information: 10545 N HAYVENHURST AVE 91344
- Application / Permit
- 21014-20000-03709
- Plan Check / Job No.
- B21VN09582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Ground floor addition to an (E) detached 2-car garage and conversion of entire building into a ADU per ordinance 186,481.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | HELEN NGUYEN |
| Corrections Issued | 8/6/2021 | HELEN NGUYEN |
| Plan Check Approved | 11/21/2021 | JOE VO |
| Issued | 12/3/2021 | APPLICANT |
| CofO in Progress | 3/10/2023 | JAVIER RAMOS JR |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
| CofO Issued | 3/29/2023 | MICHAEL SMITH |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/25/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 10/5/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/13/2022 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 1/18/2022 | Approved | MARK JOHNSON |
| Gas Test | 2/15/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/15/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 2/15/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/22/2022 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 3/2/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/7/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/28/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 5/24/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 6/6/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/15/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/15/2022 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 12/15/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/15/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/22/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 12/30/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 3/10/2023 | OK to Issue CofO | JAVIER RAMOS JR |