14621 W MINNEHAHA ST 91345
Certificate Information: 14621 W MINNEHAHA ST 91345
- Application / Permit
- 21014-20000-03705
- Plan Check / Job No.
- B21VN09566
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (10'-3"x 7'-0") LAUNDRY ROOM AND EXPAND/ ATTACHED (18'-2"x 5'-8") EXISTING GARAGE AND (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 3/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | TROY DEGUZMAN |
| Corrections Issued | 7/22/2021 | TROY DEGUZMAN |
| Building Plans Picked Up | 7/23/2021 | APPLICANT |
| Plan Check Approved | 7/28/2021 | TROY DEGUZMAN |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | JENNIFER RABUCHIN |
| CofO in Progress | 2/25/2022 | JENNIFER RABUCHIN |
| CofO Issued | 3/4/2022 | MICHAEL SMITH |
| Permit Finaled | 3/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/27/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 8/26/2021 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/30/2021 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Barrier | 8/30/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 8/30/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/30/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/8/2021 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 10/14/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/14/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/19/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/29/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/29/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/1/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/1/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| Final | 1/3/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 1/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| METHANE-Final | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/3/2022 | Approved | JENNIFER RABUCHIN |
| Final | 1/11/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Final | 1/11/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Final | 1/18/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 1/18/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/18/2022 | Approved | JENNIFER RABUCHIN |
| Final | 2/18/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/18/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/18/2022 | Approved | JENNIFER RABUCHIN |