10201 N ARLETA AVE 91331
Certificate Information: 10201 N ARLETA AVE 91331
- Application / Permit
- 21014-20000-03702
- Plan Check / Job No.
- B21VN09553
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 29' X 24'-6" IRREGULAR SHAPE ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 12/22/2021
- Issuing Office
- Current Status
- Issued on 12/22/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2021 | SERGIO MUNIZ |
| Corrections Issued | 8/2/2021 | SERGIO MUNIZ |
| Plan Check Approved | 12/22/2021 | SERGIO MUNIZ |
| Issued | 12/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/14/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/13/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/15/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 2/28/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 3/2/2022 | Approved | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 3/29/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/29/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Insulation | 3/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Barrier | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 5/9/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 5/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/9/2022 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 5/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 5/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| Final | 8/18/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/18/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 8/18/2022 | Approved | JENNIFER RABUCHIN |