2155 S LINNINGTON AVE 90025

Certificate Information: 2155 S LINNINGTON AVE 90025

Application / Permit
21014-20000-03699
Plan Check / Job No.
B21VN09549
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 8'-11" X 17'-6" ADDITION TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/22/2021
Issuing Office
Current Status
CofO Issued on 1/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2021 APPLICANT
Assigned to Plan Check Engineer 7/30/2021 RAPHAEL ROSAS
Corrections Issued 7/30/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/29/2021 RAPHAEL ROSAS
Plan Check Approved 11/24/2021 RAPHAEL ROSAS
Building Plans Picked Up 11/29/2021 APPLICANT
Issued 12/22/2021 APPLICANT
CofO in Progress 1/8/2024 STEPHANIE SWANSON
Permit Finaled 1/12/2024 DANIEL ORRANTE
CofO Issued 1/12/2024 DANIEL ORRANTE
Permit Finaled 1/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/10/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 10/18/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 10/18/2021 HISASHI KOBAYAKAWA
Construction near power lines Cleared 10/25/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 11/10/2021 ALEXANDER ANDREWS
Roof/Waste drainage to street Cleared 11/18/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Foundation To Roof Inc; Lic. No.: 767761-B 10800 SOUTH LA CIENEGA BL      INGLEWOOD, CA 90304
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/18/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 1/21/2022 Corrections Issued BRENDAN LOONEY
Underground Mechanical 1/21/2022 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 2/1/2022 Approved BRENDAN LOONEY
METHANE-Barrier 2/1/2022 Approved BRENDAN LOONEY
METHANE-Subgrade 2/1/2022 Approved BRENDAN LOONEY
Green Building Rough 4/5/2022 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 4/5/2022 Corrections Issued BRENDAN LOONEY
Wood Frame 4/5/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 4/8/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 4/8/2022 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 4/8/2022 Approved BRENDAN LOONEY
Insulation 4/27/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 4/27/2022 Partial Approval STEPHANIE SWANSON
Shower Pan 4/27/2022 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Approved EVAN COOPER
Drywall Nailing 5/9/2022 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 5/9/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 5/10/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 5/17/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/26/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 7/26/2022 Approved PATRICK QUALEY
Final 7/26/2022 Corrections Issued PATRICK QUALEY
Gas Test 7/26/2022 Approved PATRICK QUALEY
Green Building Final 7/26/2022 Approved PATRICK QUALEY
Green Building Rough 7/26/2022 Approved PATRICK QUALEY
HVAC-Final 7/26/2022 Corrections Issued PATRICK QUALEY
METHANE-Final 7/26/2022 Approved PATRICK QUALEY
METHANE-Rough 7/26/2022 Approved PATRICK QUALEY
PLUMBING-Final 7/26/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 7/26/2022 SGSOV Not Ready PATRICK QUALEY
Smoke Detectors 7/26/2022 Approved PATRICK QUALEY
Final 8/2/2022 Not Ready for Inspection PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved PATRICK QUALEY
Final 1/8/2024 OK to Issue CofO STEPHANIE SWANSON