2244 W 28TH ST 90018
Certificate Information: 2244 W 28TH ST 90018
- Application / Permit
- 21014-20000-03698
- Plan Check / Job No.
- B21VN09548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 14'3" X 15' ADDITION TO SFD TO CREATE NEW BEDROOM , BATHROOM AND CLOSET, INTERIOR REMODEL TO (E) SFD TO REMODEL BEDROOM TO ADD HALLWAY. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 2/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | RARES BODEA |
| Corrections Issued | 7/23/2021 | RARES BODEA |
| Plan Check Approved | 4/12/2022 | RARES BODEA |
| Issued | 4/13/2022 | APPLICANT |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| CofO in Progress | 2/23/2023 | SABAS ALONSO |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
| CofO Issued | 2/26/2023 | DEROLD HAUFF |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/10/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/10/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | STEVE MELGAR |
| HPOZ | Cleared | 3/21/2022 | DANIEL MATA |
| ZI | Cleared | 3/21/2022 | DANIEL MATA |
Contact Information
| Engineer | Kator,, Khaled; Lic. No.: C69781 | 19519 TULSA ST NORTHRIDGE, CA 91326 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/20/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 5/26/2022 | No Access for Inspection | SABAS ALONSO |
| METHANE-Barrier | 5/26/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 5/26/2022 | No Access for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/2/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 6/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 6/2/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 6/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Barrier | 6/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Subgrade | 6/8/2022 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 6/14/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 6/14/2022 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 6/14/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/15/2022 | Not Ready for Inspection | HORACE FULTZ |
| ELECTRICAL-Rough | 8/15/2022 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 8/15/2022 | Approved | HORACE FULTZ |
| METHANE-Rough | 8/15/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 8/15/2022 | Approved | HORACE FULTZ |
| Deputy Wood Construction | 8/17/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 8/29/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Approved | SABAS ALONSO |
| Insulation | 9/2/2022 | Approved | ANDREW BEELI |
| Drywall Nailing | 9/9/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 9/9/2022 | Approved | HORACE FULTZ |
| Shower Pan | 9/9/2022 | Corrections Issued | HORACE FULTZ |
| Shower Pan | 9/14/2022 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 9/19/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Approved | RYAN SALAZAR |
| Final | 11/3/2022 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/3/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 11/3/2022 | Approved | SABAS ALONSO |
| Final | 11/21/2022 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Not Ready | SABAS ALONSO |
| Final | 11/30/2022 | No Access for Inspection | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | No Access for Inspection | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 12/19/2022 | Approved | SABAS ALONSO |
| Final | 12/19/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Final | 12/19/2022 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | SABAS ALONSO |
| Final | 2/22/2023 | OK to Issue CofO | SABAS ALONSO |