13378 W CONTOUR DR 91423

Certificate Information: 13378 W CONTOUR DR 91423

Application / Permit
21014-20000-03696
Plan Check / Job No.
B21VN09540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING W/ ATTACHED OPEN TRELLIS. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/7/2021
Issuing Office
Current Status
Issued on 10/7/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/21/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 COLIN LOREDO
Corrections Issued 8/30/2021 COLIN LOREDO
Quality Review Completed 9/16/2021 OMID HEDAYAT
Building Plans Picked Up 9/17/2021 APPLICANT
Plan Check Approved 10/7/2021 COLIN LOREDO
Issued 10/7/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/1/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/1/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/2/2021 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 10/7/2021 ALEXANDER ANDREWS

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 10/19/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/22/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 10/29/2021 Partial Approval MICHAEL PELHAM
Green Building Rough 10/29/2021 Not Ready for Inspection MICHAEL PELHAM
Insulation 10/29/2021 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 10/29/2021 Partial Approval MICHAEL PELHAM
BUILDING-Rough-Frame 12/2/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/2/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 12/2/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 12/2/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 12/2/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/7/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 12/7/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 1/5/2022 Conditional Approval MATT KELLERMAN
Green Building Rough 1/5/2022 Conditional Approval MATT KELLERMAN
Drywall Nailing 1/20/2022 Approved MISAEL ESPARZA
Green Building Rough 1/20/2022 Approved MISAEL ESPARZA
Shower Pan 1/26/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 1/31/2022 Approved ASHLEY THOMPSON